Scrum Board Setup Tips and Tricks

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

I’d like to share with you some tips and tricks for setting up a scrum board I usually share with my clients. The bottom line is that too many tools have too many features that support old ways of thinking. Let’s look at the various items one by one.

Subtasks

Like the human tailbone, subtasks were once useful but are now mainly a source of pain. When we worked in Waterfall we measured progress with completed subtasks, but in agile when stories are short, subtasks are a burden.

A burden for developers who need to mess with subtasks using the ALM tool.

This a burden for managers who measure progress using a burndown chart that usually relies on subtasks estimation. That’s a burden because burndown charts may time tell an incorrect story (all work done but nothing is working) – progress should be measured by “done” stories, usually a burnup chart.

Using subtasks should be a choice given to developers. If you find it useful then use it. I prefer just discussing the work to be done with the other people working with me on a story. If needed we can write it down on a whiteboard, but usually, there is no need to write it down as the story is so short. We just do the job.

Showing subtasks on a scrum board takes the focus from stories getting done to subtasks. It makes the scrum board too clattered and worse of all it lets people focus on their specific job and not on the story getting done. Bad subtasks! Bad!

Swimlanes 

Another evil thing is swimlanes. Second only to subtasks.

People usually need swimlanes because there is too much information on the board. That’s indeed a problem. Many times it will be … subtasks! If it isn’t subtasks it may be either the stories are too small or the team is too big. Or maybe something else.

The idea is we need to see why are there too many items on the board and handle that problem.

The big problem with swimlanes is that it distracts you. When you have swimlanes it is difficult to see what is now in progress. This is because usually there will be items in the “to do” column which will make the swimlane too wide to see all the items in one column.

Your focus is on the things that are now in progress and that’s what you need to see.

Many times there is a swim lane per team member. This will hint that we are trying to make sure people are utilized. Like the manifesto would say, it is important to make sure people are utilized but it is more important to get stories done.

Sometimes team members ask for a swimlane per developer. This tells us that people really care only about what they need to do and not about the team. This brings us to the next item:

Story Assignee

Almost all tools allow one person to be assigned to a story. (Leankit allows many). If you want to assign more people you can use subtasks. However, we already discussed subtasks and the conclusion was quite clear.

We will usually need to assign more than one person. In many places, at least one developer and one QA will be assigned. More than that, we will be happy if people can swarm on stories – having several people working on one story is fun and contributes to teamwork and thus very effective.

So, what do we do?

Many tools allow the addition of custom fields. For instance, Jira. I usually recommend clients working with Jira add a custom field called “assigned team members”. The field type should be multi-select. You will need to manually add the list of all team members. Once you do that you ask the tool to present the information on the card on the board and suddenly – voila! You have a strong scrum board where you see the people involved in every story. That’s great.

Last but not least – Columns

Most tools start with the standard “To Do – Doing – Done” columns + a backlog. (read here about the critical difference between backlog and to-do). That’s great! Why touch it? Please don’t.

Many teams will add a “Test” column. And a “pull request” column. And there are more.

The problem with these additional columns is that they are good excuses for things getting stuck. If there is a “dev” column and a “Test” column it means it is really all right to finish dev (I’m done!) and QA can be done later. Reminds you of subtasks? correct, it is similar.

If the sprint is only two weeks long and stories are short, there should be no reason for these additional columns. Just get done with the story – and please no stories! Remember we already have the names of all involved people on the card – just get it done with.

Conclusion

A scrum board should be very simple. There is a list of stories to do. Some are in progress, some are already done. We know who is working on what. That’s it. Don’t let fancy features distract you.

You may be interested in one of our Agile Up! workshops where we help you use popular Agile ALM tools such as Jira and TFS more effectively.

Subscribe for Email Updates:

Categories:

Tags:

Risk Management on Agile Projects
AgileSparks
Quality Assurance
ARTs
Agility
Agile Product Ownership
Systems Thinking
ATDD
What Is Kanban
Lean Software Development
PI Planning
Lean Agile
lean agile change management
Large Scale Scrum
Atlassian
Artificial Intelligence
Lean Agile Organization
BDD
Agile Israel Events
Daily Scrum
Webinar
Advanced Roadmaps
Portfolio for Jira
SAFe
Agile Product Development
Professional Scrum Master
Reading List
Agile in the Enterprise
Slides
Lean and Agile Techniques
LeSS
The Agile Coach
Perfection Game
Enterprise DevOps
Kanban Kickstart Example
ScrumMaster Tales
Applying Agile Methodology
Product Management
EOS®
Nexus and SAFe
Process Improvement
Acceptance Test-Driven Development
Kaizen Workshop
Agile Project Management
Agile Release Planning
Kanban
Agile for Embedded Systems
Self-organization
chatgpt
Product Ownership
Agile Israel
Certification
Scrum and XP
Kanban Game
Sprint Iteration
Scrum Master
Implementation of Lean and Agile
Risk-aware Product Development
DevOps
Agile
Scrum With Kanban
Entrepreneurial Operating System®
Team Flow
Atlaassian
Built-In Quality
Lean-Agile Software Development
Professional Scrum with Kanban
Lean Agile Leadership
Accelerate Value Delivery At Scale
Agile Community
Legacy Enterprise
Iterative Incremental Development
Agile Mindset
Nexus and Kanban
Scrum.org
Scaled Agile Framework
Legacy Code
Code
SAFe Release Planning
Agile Project
Program Increment
Agile Basics
ATDD vs. BDD
ROI
Continuous Integration
GanttBan
Manage Budget Creation
The Kanban Method
System Archetypes
LAB
Sprint Retrospectives
Agile Testing Practices
Agile Contracts Best Practices
Nexus
Presentation
Lean Budgeting
Agile Risk Management
PI Objectives
Professional Scrum Product Owner
Introduction to Test Driven Development
Frameworks
Scrum Master Role
Agile Assembly Architecture
ALM Tools
Kanban 101
Jira admin
Risk Management in Kanban
Certified SAFe
Story Slicing
AI
speed at scale
Lean Agile Basics
Pomodoro Technique
Continuous Deployment
An Appreciative Retrospective
Achieve Business Agility
QA
Lean Risk Management
Development Value Streams
Agile Exercises
Agile Delivery
Agile Techniques
Covid19
SPC
Planning
Scrum Primer
Agile Development
Games and Exercises
Principles of Lean-Agile Leadership
SA
Change Management
Agile Games
Kanban Basics
Agile Program
IT Operations
Agile Games and Exercises
Kaizen
Business Agility
WIP
agileisrael
Agile Release Management
Release Train Engineer
Tools
Nexus vs SAFe
RSA
Test Driven Development
RTE Role
Continuous Planning
Jira Plans
User stories
Value Streams
Coaching Agile Teams
Operational Value Stream
Continuous Delivery
Spotify
Managing Projects
Implementing SAFe
Keith Sawyer
Scrum Values
Elastic Leadership
Agile Marketing
Limiting Work in Progress
Software Development Estimation
Engineering Practices
A Kanban System for Software Engineering
Releases Using Lean
Lean Agile Management
TDD
speed @ scale
LPM
ART Success
AI Artificial Intelligence
Continuous Improvement
Nexus Integration Team
Scrum
Jira
System Team
Scrum Guide
SAFe DevOps
Rapid RTC
Lean-Agile Budgeting
Effective Agile Retrospectives
Agile India
Software Development
Jira Cloud
NIT
RTE
Lean Startup
Introduction to ATDD
Amdocs
Video
System Integration Environments
POPM
Lean and Agile Principles and Practices
Hybrid Work
Agile Outsourcing
Managing Risk on Agile Projects
Tips
Sprint Planning
Agile and DevOps Journey
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart