A different approach to estimations in SAFe

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

SAFe™ (The Scaled Agile Framework) uses Story Points throughout the various levels as its estimation currency. This is covered in the “Story” article on the SAFe site. This is a pretty standard practice in organizations scaling agile these days. If you dive a bit deeper into how this is done in SAFe you will see that actually the story points used in SAFe are quite similar to “Ideal Developer Day” as this helps the teams align to a common baseline and support a rational economic ROI discussion at the level of Features/Capabilities that require effort from more than one team or haven’t even been mapped to a specific team yet.

An alternative to using Story Points at the team level that is interesting to look at especially as Kanban is becoming a first-class citizen of the SAFe world is to use NoEstimates.

In essence, this means not trying to estimate the size of the work just slicing work into a size that we can bite on and turn around quickly. To get a quick grasp cards-legend-non-explicit-rotated-b43a891a4ea2f2300bc84fcbee6c3bb6of it think of replacing your classic Fibonacci planning poker cards with a set of cards saying 1, TFB (Too Frighteningly Big), NFC (No Faintest Clue). This approach is rising in popularity among Kanban/ScrumBan practitioners – We’ve been looking at the “Iteration Planning” process for years trying to address some of its wastes/tensions.

This “No Estimates” inspired approach to story estimation in PI Planning has a couple of benefits:

  • It is faster – which comes in handy during PI Planning.
  • It forces teams to slice into smaller stories which is better.
  • It is naturally easier to baseline/align multiple teams around the same definition. (BTW a 1 here would be something like a 3 or 5 in the classic SAFe velocity calculation – a story that takes the team about 3 days to develop and 3 days to test)

Iteration Planning becomes even easier – Just understand your velocity and how many stories you can fit. Minimal time is spent estimating.

There are a couple of challenges though. Forcing the team to split their whole Feature into small 1-size stories including those that are only going to be pulled in later iterations in the PI might be a waste of time.

Another challenge is how to make rational economic decisions at the Feature/Capability and even Epic level without estimates. #NoEstimates die-hards say it doesn’t make sense to estimate even at this level, not just the stories level. I’m not convinced. What I typically do in cases where teams stop estimating story sizes is just use story counts as the currency at the higher levels. So instead of saying “This seems to be a 20 Story Points Feature” we would say “This Feature seems to be something around 20 stories” meaning we ESTIMATE it will map to about 20 stories when we eventually slice it. We DON’T slice it to stories in order to estimate. We reach that estimation using a classic relative estimate approach like Planning Poker / Team Estimation Game. This is actually something that helps with the first challenge as well. Knowing that we’re dealing with a Feature that we think has about 20 stories and that we identified 7 stories for the first iteration and 4 stories for the second, we might say something like there are around 9 stories more for the third iteration or even better – let’s look at the remaining chunk and compare that to our feature estimation scale and see how many stories we think there are there.

Of course, if we think there are dragons (a.k.a dependencies) hidden in this remaining chunk we should make the effort to slice it into smaller stories and work out the dependencies/scheduling with the other teams on the train.

I’ve done this with clients in the trenches. Based on this experience, I consider this alternative approach to estimation a legitimate alternative to Story Points estimation at the SAFe Team Level.

This blog post was originally posted on Yuval’s personal blog back in 2016.  

Subscribe for Email Updates:

Categories:

Tags:

Managing Risk on Agile Projects
Code
Enterprise DevOps
Lean Startup
Lean-Agile Budgeting
Continuous Integration
Agile
Sprint Planning
Continuous Planning
Large Scale Scrum
Introduction to Test Driven Development
Introduction to ATDD
Agile for Embedded Systems
Kanban 101
Lean Budgeting
Agile Games
Agile Release Planning
A Kanban System for Software Engineering
Continuous Improvement
Lean Agile Basics
Frameworks
Lean and Agile Principles and Practices
Product Management
Legacy Enterprise
Webinar
ATDD
Nexus
Jira Cloud
Lean and Agile Techniques
Covid19
Applying Agile Methodology
SAFe Release Planning
chatgpt
EOS®
Achieve Business Agility
System Archetypes
Kanban Game
RTE
Operational Value Stream
Lean Software Development
Agile Marketing
ALM Tools
Agile Games and Exercises
Agile Testing Practices
RTE Role
Manage Budget Creation
Value Streams
Agile Israel
Atlassian
DevOps
Games and Exercises
predictability
Certified SAFe
Release Train Engineer
Agile Risk Management
Process Improvement
Kaizen Workshop
WIP
Agile Techniques
Jira
SAFe DevOps
Agile and DevOps Journey
Professional Scrum Product Owner
Kaizen
SA
Lean-Agile Software Development
speed at scale
Portfolio for Jira
SAFe
Nexus vs SAFe
ROI
Legacy Code
System Team
User stories
Agile Exercises
Software Development Estimation
Agile Product Development
Reading List
AI Artificial Intelligence
Planning
Sprint Retrospectives
Continuous Deployment
ART Success
Agile Development
Story Slicing
Hybrid Work
Pomodoro Technique
POPM
Rapid RTC
Video
Scrum.org
Scrum Master Role
lean agile change management
Kanban
Agile Project Management
Keith Sawyer
Presentation
Agile Basics
Spotify
Scrum and XP
Engineering Practices
Elastic Leadership
Lean Agile Organization
ARTs
Iterative Incremental Development
An Appreciative Retrospective
Risk Management on Agile Projects
Agile Outsourcing
Tips
Scrum With Kanban
Program Increment
RSA
Agile Release Management
Software Development
Releases Using Lean
Built-In Quality
Continuous Delivery
Acceptance Test-Driven Development
NIT
ScrumMaster Tales
Entrepreneurial Operating System®
Agile India
speed @ scale
System Integration Environments
Daily Scrum
Team Flow
BDD
Implementing SAFe
PI Objectives
Agile Mindset
Jira Plans
Scrum
Agile Israel Events
Professional Scrum Master
IT Operations
Scrum Guide
Nexus and SAFe
Jira admin
QA
LAB
Agile Contracts Best Practices
AI
Slides
Agility
Agile in the Enterprise
Nexus and Kanban
SPC
Agile Assembly Architecture
Lean Risk Management
Test Driven Development
Scrum Master
Agile Delivery
Change Management
Business Agility
Nexus Integration Team
Amdocs
Effective Agile Retrospectives
Scrum Values
Risk-aware Product Development
Implementation of Lean and Agile
Professional Scrum with Kanban
LPM
Lean Agile Leadership
Kanban Basics
LeSS
Agile Project
Agile Community
Lean Agile
Risk Management in Kanban
The Agile Coach
Limiting Work in Progress
Principles of Lean-Agile Leadership
Systems Thinking
agileisrael
Perfection Game
AgileSparks
Self-organization
Agile Program
PI Planning
Scaled Agile Framework
Scrum Primer
Product Ownership
Lean Agile Management
The Kanban Method
Managing Projects
Development Value Streams
ATDD vs. BDD
Sprint Iteration
Agile Product Ownership
Coaching Agile Teams
Advanced Roadmaps
Quality Assurance
TDD
Accelerate Value Delivery At Scale
Artificial Intelligence
Kanban Kickstart Example
What Is Kanban
GanttBan
Tools
Certification
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart