The Critical Difference Between Backlog and To Do (Kanban, Scrum)

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

When we build a kanban board to manage our work (either practicing Kanban or Scrum) we usually create a Backlog list (usually the first column) and a To Do list (following the Backlog). I’ve noticed that many times the separation between the two is artificial and people don’t always understand the critical difference between the two. I’d like to discuss it here.

The Backlog

The backlog is a list of things we think we should do, for many reasons (clients, our own needs, etc.). Moreover, it is prioritized, so things on the top are things we really really want (or need) to do while things at the bottom are probably fantasies that will never happen.

For instance, the backlog of an airport is all the flights and the backlog of a road system is all the cars that need to go somewhere. And the backlog of a development team is all the software that needs to be developed.

As stuff goes up in priority it becomes more concrete and more focused, shedding off redundant things, like a baby growing up and losing their baby fat. This process is called backlog grooming or backlog refinement. And still, the backlog is a list of things we want to do, we should do, we need to do – even the topmost items. Not more than that.

The To Do

The To Do is a list of things we decided to do now because we believe that we can accomplish them in high quality and timely manner. This is a big decision. Moving something from the Backlog to To-Do takes a lot of responsibility. You should consider it gravely. The hand holding the note, moving it from Backlog to To Do (or more likely, firmly grasping the mouse) should tremble.

Once you decide to do something, you want to do it very quickly. This is our cycle time. The shorter our cycle time is, the more focused we are, the chances for things going astray are lower, the chances for us changing our mind midway are smaller and many other good things – see Don Reinertsen’s book Product Development Flow for the full list. Mr. Reinertsen gives airplanes as an example. I’ll extend it a bit: airplanes should start boarding only when it is known that the airplane can freely taxi to the runway and then land directly without circling. Imagine how much time would be saved. And the same goes for traffic over a road. Imagine a system that could tell you when to go out of the house so traffic won’t be congested.

When the team has available capacity (or in Scrum during the planning meeting) the team makes this decision. The team decides they will do something. If they think it is not yet ready they should keep it in the backlog. Ready for what? Ready for the way the team machine knows to process stuff. The team calibrates the way they work and the stuff going into the machine should fit this. It is a matter of practice for the team to know how to better work together.

The same goes for an organization now planning to do something in the next quarter – once they decide they want to do it they should do everything they can to make it progress very fast.

Grooming

Of course, there’s a trade-off between how much you invest in an item when it’s in the backlog and later. Investing while it is in the backlog will increase predictability on one hand, but on the other hand, it will increase the number of things you do in parallel which results in less focus and more waste due to context switching. You need to find the right balance.

In a sense, knowing when an item is ready for development is similar to knowing when a fruit is ripe – read more about it here.

Breaking It Down

And what if something is really big? We can’t do it really fast, but we do it in small pieces, small pieces that make sense. We do it so that once we’re done with a piece we have something complete (even a draft) that can provide us with information on how to continue.

I found that, as I have a degree in procrastination, doing things that take very little time is a miracle. I lose focus very fast so if I want to complete something I need to complete it fast. But so does an organization, right? How focused is your organization?

Once you practice doing things very fast, in the required quality, you actually complete stuff.

Another advantage of cutting things down is that you are able to remove the redundant scope.

Mixing It All Up

The problem starts when we mix the Backlog with the To Do when things we should do somehow become things we do. People in a car want to get to their destination in the morning and immediately they start driving. Then we get congestion. Projects arrive at the company and we immediately start development. Then we get congestion.

But why does it happen? Why do we mix the Backlog and the To Do?

First, it is easier to just start. It is easier to manage. There is something you need to do and you just do it. It is easier to manage when you react. It is easier for every driver to go out of their parking and start driving rather than waiting for some sign to start driving.

Second, it feels much better to start doing things you should do. We are industrious people and when there’s a job to do we make a plan and start doing it. I remember as a kid I was told the best way to do homework was to do it the day you got it. It stands against our intuition not to start something we need to do.

We need to learn to make the differentiation between what we need to do, what we should do, what we want to do, and what we are doing, between the Backlog and the To Do. This separation will help us to focus on what we do, complete it when we need it, in the right quality, and eventually do more and better than we do today.

More to read:

The Professional Developer

Understanding the relationship between Kanban and the Theory of Constraints Critical Chain Project Management Approach

User Stories don’t belong in the Marketing Backlog

How Leaders can support and leverage the Scrum Artifacts

Agile Product Management​ (APM)

 

Subscribe for Email Updates:

Categories:

Tags:

Agile India
Continuous Improvement
ROI
Managing Risk on Agile Projects
RTE
Reading List
Artificial Intelligence
Agile Mindset
Large Scale Scrum
ScrumMaster Tales
TDD
A Kanban System for Software Engineering
Continuous Planning
Atlassian
ALM Tools
Kaizen
DevOps
Nexus Integration Team
AI
Scrum Guide
Atlaassian
Scrum and XP
Agile Project Management
Implementation of Lean and Agile
Scrum Primer
speed @ scale
Kaizen Workshop
Agile Program
EOS®
Introduction to Test Driven Development
Jira Cloud
Agile Assembly Architecture
SAFe DevOps
ART Success
Program Increment
Applying Agile Methodology
GanttBan
Kanban
Elastic Leadership
QA
Enterprise DevOps
Agile Community
Agile Outsourcing
Frameworks
Change Management
Certified SAFe
ATDD vs. BDD
Advanced Roadmaps
PI Planning
Agile Games and Exercises
Lean-Agile Budgeting
Professional Scrum with Kanban
Risk-aware Product Development
AgileSparks
Legacy Enterprise
Kanban Kickstart Example
System Integration Environments
Perfection Game
ATDD
PI Objectives
Risk Management in Kanban
lean agile change management
Keith Sawyer
Risk Management on Agile Projects
Limiting Work in Progress
Lean Software Development
AI Artificial Intelligence
Managing Projects
Team Flow
Amdocs
RTE Role
agileisrael
Professional Scrum Product Owner
Scrum Master
Agile Basics
Kanban 101
Accelerate Value Delivery At Scale
Coaching Agile Teams
Agile Risk Management
User stories
Code
The Kanban Method
Scaled Agile Framework
Agile Israel
Pomodoro Technique
Planning
Jira
Agile Product Development
Video
Engineering Practices
Achieve Business Agility
SPC
Tips
Operational Value Stream
Iterative Incremental Development
Lean Agile Management
Lean and Agile Principles and Practices
Implementing SAFe
BDD
Lean Budgeting
Introduction to ATDD
Lean and Agile Techniques
Webinar
Nexus and Kanban
Lean Agile
SA
Product Ownership
What Is Kanban
Kanban Basics
Jira Plans
LPM
Agile Israel Events
Agile Contracts Best Practices
Tools
Lean Agile Leadership
Scrum Values
Agile Release Planning
Software Development Estimation
SAFe Release Planning
Systems Thinking
Lean Agile Basics
Software Development
Release Train Engineer
Agile in the Enterprise
Nexus vs SAFe
Entrepreneurial Operating System®
Agile Marketing
Product Management
Agile Product Ownership
Games and Exercises
Manage Budget Creation
speed at scale
Sprint Iteration
NIT
Rapid RTC
Business Agility
Acceptance Test-Driven Development
Agile Techniques
System Team
Scrum Master Role
Development Value Streams
Agile and DevOps Journey
Covid19
POPM
Sprint Retrospectives
Agility
LeSS
Professional Scrum Master
Agile Development
Agile Testing Practices
predictability
Agile for Embedded Systems
Nexus and SAFe
Effective Agile Retrospectives
Agile Delivery
Sprint Planning
Story Slicing
Portfolio for Jira
Lean Risk Management
IT Operations
Value Streams
Agile Release Management
Principles of Lean-Agile Leadership
Lean Agile Organization
Agile
chatgpt
Jira admin
Agile Exercises
Process Improvement
Scrum With Kanban
Hybrid Work
Test Driven Development
Certification
An Appreciative Retrospective
Quality Assurance
WIP
Spotify
Scrum.org
Scrum
LAB
Releases Using Lean
Kanban Game
System Archetypes
Continuous Deployment
Lean Startup
Daily Scrum
Continuous Delivery
Nexus
RSA
Self-organization
SAFe
Agile Project
The Agile Coach
Legacy Code
Built-In Quality
Lean-Agile Software Development
Agile Games
Slides
ARTs
Presentation
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart