Iterating faster with SAFe

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

Here’s a frequently asked question in the SAFe community: I wanted to understand what SAFe says about someone who wants to go faster than 2 weeks of iteration? I mean the whole PI concept is based on 5 iterations worth of planning. What if a team/organization wants to develop and synchronize faster than 2 weeks? Is speed going to be compromised by following the standards of PI cadence?

Here’s my take:

Adjusting Cadence Length in SAFe – Can you? Should you?

SAFe considers the 2-week iteration length as a default rather than a rule.

The question you need to consider is what inspection and adaptation cycle you’re looking to accelerate – the Iteration or the PI.

Basically, do you want an opportunity to tactically adjust priorities more frequently than every 2w? Or do you want to adjust a more strategic direction more often than every 8-12w?

With the answer to that, you can experiment either with iteration length and/or PI length. Of course, the cadence length affects coordination overhead – there’s a fine balance.

Additionally, we’re talking about a Planning, Inspection, and Adaptation cadence – NOT the release cadence. Releases are on-demand meaning can be more frequent (or less).

Iteration Goals and PI Objectives provide us with room to maneuver

Another point to remember is that you can adjust iteration backlogs as long as you’re focusing on iteration goals. And even PI objectives can be adjusted – “Assume Variability Preserve Options”. If it’s occasional adjustment it’s not a reason to necessarily use a faster cadence.

Is team-level Kanban the solution to the need for more flexibility in SAFe?

Many teams think Kanban might be the best choice for them if they need more and more flexibility. Kanban CAN be a better fit if your demand is extremely volatile. I would be very careful though. Doing some level of goal-setting and prioritization and planning on a cadence is a powerful way for a team to focus. Do we really WANT to be a strictly reactive team?

Kanban combined with flexibility with some of the capacity we have each iteration can definitely be helpful and is why we recommend all Agile Teams in SAFe use Kanban to limit their WIP and improve their flow – this actually enables them to change scope even within an Iteration if that’s needed in order to achieve their Goal. (see my recent blog post that talks about dynamic scope in SAFe).

“Kanban Teams” in SAFe have an iteration cadence with the establishment of iteration goals even if not detailed iteration backlogs. Maybe that’s a good fit for your context maybe not. It might be an interesting experiment to try.

What if Planning a PI doesn’t make sense?

Finally, if PI planning doesn’t make sense even if PI is shorter – maybe you need to reflect on SAFes appropriateness for your context or on what’s so volatile about the demand coming your way and whether it’s “nature of the beast” or a systemic impediment to work on …

What’s the Bottom Line

What I tried to show here is that a conversation about what to do when the iteration feels too long should start with “Why”. Get to the bottom of what’s currently not ideal, look at the different options, consider Lean, Agile, and SAFe principles, and figure out whether it makes sense to change the cadence, change your approach to the balance between planning and flexibility, the difference between committing to goals and committing to backlogs, and the role that more flow-oriented techniques such as Kanban can play in addressing your issue.

Interested to hear any thoughts or experiences. Leave us a comment !

Subscribe for Email Updates:

Categories:

Tags:

Lean Agile Basics
Reading List
Lean-Agile Software Development
Introduction to Test Driven Development
Development Value Streams
ROI
AgileSparks
Agile Marketing
Scrum Master
Nexus
Change Management
Perfection Game
Risk Management on Agile Projects
RTE Role
Atlassian
Scrum and XP
Built-In Quality
ART Success
Rapid RTC
ATDD
Sprint Planning
Tips
speed at scale
Business Agility
Lean and Agile Principles and Practices
Scrum.org
Elastic Leadership
Agile Israel Events
Agile Product Development
Risk-aware Product Development
Enterprise DevOps
Professional Scrum Product Owner
Code
IT Operations
Quality Assurance
Risk Management in Kanban
BDD
Kanban
Product Ownership
Agile Outsourcing
Implementing SAFe
Atlaassian
Continuous Delivery
Managing Risk on Agile Projects
Certification
Agile Risk Management
Lean Software Development
Lean Startup
Agile for Embedded Systems
Lean Agile Organization
User stories
Large Scale Scrum
Spotify
Story Slicing
Nexus and Kanban
SA
AI Artificial Intelligence
Agile Delivery
Program Increment
Implementation of Lean and Agile
TDD
lean agile change management
NIT
Planning
Scaled Agile Framework
Manage Budget Creation
Presentation
Agile Release Planning
Agile Project Management
Nexus Integration Team
Agile Israel
Accelerate Value Delivery At Scale
Software Development Estimation
Nexus vs SAFe
Lean Agile
Frameworks
System Integration Environments
Systems Thinking
Artificial Intelligence
Agile Community
Agile India
Sprint Retrospectives
Continuous Improvement
POPM
Scrum Primer
Continuous Integration
Kaizen Workshop
Entrepreneurial Operating System®
AI
Agile Contracts Best Practices
Agile Mindset
Test Driven Development
ARTs
Product Management
Kanban Basics
Effective Agile Retrospectives
Agile in the Enterprise
Agile Testing Practices
LAB
PI Objectives
Games and Exercises
Lean Agile Leadership
Process Improvement
System Team
SPC
ATDD vs. BDD
Introduction to ATDD
LeSS
Limiting Work in Progress
SAFe Release Planning
Agile Program
Software Development
EOS®
RTE
LPM
Lean-Agile Budgeting
Keith Sawyer
Agile Release Management
RSA
Amdocs
Webinar
Value Streams
Nexus and SAFe
Legacy Enterprise
Pomodoro Technique
Scrum Guide
Jira Plans
System Archetypes
DevOps
The Agile Coach
Engineering Practices
Agile Exercises
Kanban 101
ScrumMaster Tales
Applying Agile Methodology
Lean Risk Management
Kanban Game
Agile and DevOps Journey
SAFe
Iterative Incremental Development
Agile Basics
An Appreciative Retrospective
Release Train Engineer
GanttBan
Professional Scrum Master
Advanced Roadmaps
Team Flow
Lean Agile Management
Legacy Code
Continuous Deployment
Acceptance Test-Driven Development
Self-organization
Scrum Values
Certified SAFe
Kaizen
Jira Cloud
Agile
Professional Scrum with Kanban
Agile Games
Covid19
Scrum With Kanban
PI Planning
Agile Games and Exercises
Scrum Master Role
WIP
Video
The Kanban Method
Agile Product Ownership
Agile Development
predictability
Daily Scrum
Jira admin
Continuous Planning
SAFe DevOps
Managing Projects
Tools
QA
Releases Using Lean
agileisrael
ALM Tools
Slides
Kanban Kickstart Example
chatgpt
Coaching Agile Teams
Lean Budgeting
Lean and Agile Techniques
Jira
A Kanban System for Software Engineering
speed @ scale
Operational Value Stream
Agility
Agile Project
Sprint Iteration
Principles of Lean-Agile Leadership
Agile Techniques
Portfolio for Jira
Scrum
Hybrid Work
What Is Kanban
Agile Assembly Architecture
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart