Iterating faster with SAFe

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

Here’s a frequently asked question in the SAFe community: I wanted to understand what SAFe says about someone who wants to go faster than 2 weeks of iteration? I mean the whole PI concept is based on 5 iterations worth of planning. What if a team/organization wants to develop and synchronize faster than 2 weeks? Is speed going to be compromised by following the standards of PI cadence?

Here’s my take:

Adjusting Cadence Length in SAFe – Can you? Should you?

SAFe considers the 2-week iteration length as a default rather than a rule.

The question you need to consider is what inspection and adaptation cycle you’re looking to accelerate – the Iteration or the PI.

Basically, do you want an opportunity to tactically adjust priorities more frequently than every 2w? Or do you want to adjust a more strategic direction more often than every 8-12w?

With the answer to that, you can experiment either with iteration length and/or PI length. Of course, the cadence length affects coordination overhead – there’s a fine balance.

Additionally, we’re talking about a Planning, Inspection, and Adaptation cadence – NOT the release cadence. Releases are on-demand meaning can be more frequent (or less).

Iteration Goals and PI Objectives provide us with room to maneuver

Another point to remember is that you can adjust iteration backlogs as long as you’re focusing on iteration goals. And even PI objectives can be adjusted – “Assume Variability Preserve Options”. If it’s occasional adjustment it’s not a reason to necessarily use a faster cadence.

Is team-level Kanban the solution to the need for more flexibility in SAFe?

Many teams think Kanban might be the best choice for them if they need more and more flexibility. Kanban CAN be a better fit if your demand is extremely volatile. I would be very careful though. Doing some level of goal-setting and prioritization and planning on a cadence is a powerful way for a team to focus. Do we really WANT to be a strictly reactive team?

Kanban combined with flexibility with some of the capacity we have each iteration can definitely be helpful and is why we recommend all Agile Teams in SAFe use Kanban to limit their WIP and improve their flow – this actually enables them to change scope even within an Iteration if that’s needed in order to achieve their Goal. (see my recent blog post that talks about dynamic scope in SAFe).

“Kanban Teams” in SAFe have an iteration cadence with the establishment of iteration goals even if not detailed iteration backlogs. Maybe that’s a good fit for your context maybe not. It might be an interesting experiment to try.

What if Planning a PI doesn’t make sense?

Finally, if PI planning doesn’t make sense even if PI is shorter – maybe you need to reflect on SAFes appropriateness for your context or on what’s so volatile about the demand coming your way and whether it’s “nature of the beast” or a systemic impediment to work on …

What’s the Bottom Line

What I tried to show here is that a conversation about what to do when the iteration feels too long should start with “Why”. Get to the bottom of what’s currently not ideal, look at the different options, consider Lean, Agile, and SAFe principles, and figure out whether it makes sense to change the cadence, change your approach to the balance between planning and flexibility, the difference between committing to goals and committing to backlogs, and the role that more flow-oriented techniques such as Kanban can play in addressing your issue.

Interested to hear any thoughts or experiences. Leave us a comment !

Subscribe for Email Updates:

Categories:

Tags:

Business Agility
WIP
Team Flow
Scrum Primer
A Kanban System for Software Engineering
Agile Project
Code
Kaizen Workshop
Games and Exercises
Story Slicing
Hybrid Work
Jira
Process Improvement
Lean and Agile Principles and Practices
Coaching Agile Teams
Spotify
Lean Software Development
Covid19
chatgpt
Scrum Master
Product Management
Risk-aware Product Development
Continuous Planning
What Is Kanban
Tools
Large Scale Scrum
SPC
speed @ scale
EOS®
POPM
Agile Techniques
Agile Exercises
Lean Risk Management
Agile Games
lean agile change management
Agile Contracts Best Practices
Agile Assembly Architecture
RSA
TDD
Nexus Integration Team
Lean and Agile Techniques
Daily Scrum
PI Planning
Rapid RTC
Artificial Intelligence
Quality Assurance
Reading List
Slides
GanttBan
Implementation of Lean and Agile
agileisrael
ARTs
Tips
Keith Sawyer
SAFe Release Planning
RTE
RTE Role
Applying Agile Methodology
System Archetypes
Program Increment
ATDD vs. BDD
AI Artificial Intelligence
speed at scale
Webinar
Principles of Lean-Agile Leadership
Professional Scrum with Kanban
Achieve Business Agility
Perfection Game
Introduction to ATDD
Continuous Integration
Agile Product Development
Agile and DevOps Journey
Kanban Basics
NIT
Manage Budget Creation
Elastic Leadership
predictability
Continuous Deployment
Agile India
Managing Risk on Agile Projects
QA
Agile for Embedded Systems
Kanban 101
Nexus and SAFe
Sprint Iteration
Lean Budgeting
Releases Using Lean
Acceptance Test-Driven Development
The Kanban Method
Lean Agile Management
Agile in the Enterprise
Certified SAFe
Portfolio for Jira
Agile Basics
PI Objectives
Limiting Work in Progress
User stories
Sprint Planning
Agility
Professional Scrum Master
Jira Plans
Agile Release Planning
Kanban Game
Agile Delivery
ATDD
Scrum
Kaizen
Jira Cloud
LeSS
Lean Agile Organization
Lean Agile
Agile Program
Enterprise DevOps
Agile Outsourcing
Nexus vs SAFe
IT Operations
Scrum Values
Advanced Roadmaps
Test Driven Development
Agile Games and Exercises
Release Train Engineer
Introduction to Test Driven Development
Risk Management in Kanban
Jira admin
Presentation
Scaled Agile Framework
Lean Agile Leadership
Atlassian
Continuous Improvement
Video
ART Success
ALM Tools
Nexus and Kanban
Legacy Code
The Agile Coach
Lean-Agile Budgeting
Agile
Atlaassian
SA
Entrepreneurial Operating System®
Agile Israel
Accelerate Value Delivery At Scale
System Team
SAFe DevOps
AI
Scrum With Kanban
Agile Release Management
LAB
Agile Israel Events
DevOps
Agile Product Ownership
Continuous Delivery
Lean Agile Basics
Frameworks
AgileSparks
Agile Risk Management
ROI
System Integration Environments
Kanban
BDD
Certification
Agile Project Management
Scrum and XP
SAFe
Risk Management on Agile Projects
Professional Scrum Product Owner
Sprint Retrospectives
Scrum Master Role
Implementing SAFe
An Appreciative Retrospective
Software Development
LPM
Agile Marketing
Engineering Practices
Self-organization
Value Streams
Agile Community
Managing Projects
Planning
Pomodoro Technique
Software Development Estimation
Operational Value Stream
Iterative Incremental Development
Effective Agile Retrospectives
Systems Thinking
Scrum.org
Change Management
Scrum Guide
Built-In Quality
Lean Startup
Product Ownership
Agile Testing Practices
Amdocs
Agile Mindset
Nexus
Legacy Enterprise
ScrumMaster Tales
Lean-Agile Software Development
Development Value Streams
Agile Development
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart