Co-Creating and teaching the new Scrum.org Professional Scrum with Kanban class has given me an opportunity to get back to geeking out on WIP limits, flow metrics, and all things Kanban. And it’s been fun!

One of the key Kanban practices is Limiting Work in Progress. If you want to be pedantic, actually what this practice aims for is Reducing and stabilizing Work in Progress. This improves flow, provides predictability, and is actually even more important for creating a pull-based Kanban system than visualizing your workflow using a Kanban board. I worked with several clients who limited their WIP but didn’t use Kanban boards. One could argue that maybe this practice deserves to be first in the list of Kanban practices, ahead of Visualization.

Anyhow, when a Scrum Team implements Kanban they should definitely figure out how to limit and reduce their Work in Progress. This is a key part of their definition of “Workflow”. First of all, when we say flow we mean flow of valuable items – so flow of PBIs (rather than tasks).

Now, a question comes up: Who should define the WIP Limit? Let’s assume the team is using Kanban to improve the Sprint flow by visualizing and managing flow in the Sprint Backlog. Sprint Backlog is owned by the Development Team so it would make sense for them to own their workflow and specifically the WIP limits in this case.

What if the team is using Kanban from a more holistic perspective, starting from the Product Backlog and including refinement work as well? In this case, it would be the Scrum Team that would own the workflow and therefore would need to discuss WIP limits.

Now, what if the Dev Team actually wants to involve the Product Owner in their Sprint flow – e.g. to review and accept a story during the Sprint before it goes through testing? Who decides whether to do this? Who owns the Sprint Backlog in this case? I think it is the Scrum Team.

Ok, so we understand who defines workflow and therefore WIP limits. Now let’s assume a team is mid-Sprint and there’s an important valuable item the Product Owner wants to add to the Sprint Backlog. It is aligned with the Sprint Goal. The team is currently at its WIP Limit. Could they add this item? Should they? What needs to happen to the WIP limit?

My take on this is that first of all a decision needs to be made on whether to pull this item into the Sprint Backlog. This discussion isn’t related to Kanban at all. It is a core Scrum question and the answer is that it is up to the team to agree to pull a new item into the Sprint Backlog. The Sprint Goal can be used to assess how aligned this item is with the current focus.

In case the item is pulled into the Sprint Backlog, then the Dev Team needs to figure out whether they can actually start it right away. This depends on the WIP limits and the current WIP. If the team is at their WIP they shouldn’t pull in that new item until some room frees up. If their backlog items are pretty small, an empty WIP slot will free up pretty quickly. If items are big, it can take a while.

The longer it might take to get a normal pull slot ready, the more pressure there might be to actually expedite this card. What is expediting? going beyond the current WIP limits and pushing this item along on top of the existing flow. The typical way to do this is NOT to change the WIP limit definition but to go above WIP and note a WIP exception. These exceptions can then be a topic for inspection and adaptation come time to retrospect.

In general, I don’t recommend changing WIP limits on a whim just because there seems to be a need during the Sprint. I’d rather see an exception and discussion rather than hide the problem under a policy change. Most of the time, Scrum Teams should adjust WIP limits during the Sprint Retrospective out of an attempt to create a better flow strategy, not a way to manage at the tactical level. This is similar to the definition of Done. We don’t change the definition of Done during a sprint just because we have a problem creating a Done Increment. We note the exception, maybe even fail to create a really Done Increment, and we discuss the definition during our Retrospective.

One last thing to note about limiting WIP is that while we typically talk about limiting WIP as per-lane constraints on your workflow, this is actually just one specific way to do it. You could limit the amount of work in progress per person, per the entire team throughout their workflow, or actually, you could limit WIP by time. E.g. “we won’t work on more than 10 items this week”. Hey – that sounds familiar! #SprintForecast.

NOTE: Updated to emphasize that we want to limit WIP by valuable PBIs (rather than tasks). Thanks, Giora for suggesting to make that explicit.

Subscribe for Email Updates:

Categories:

Tags:

Release Train Engineer
ROI
lean agile change management
Agile Project Management
Advanced Roadmaps
Professional Scrum Master
Agile Outsourcing
Agile Mindset
Frameworks
Professional Scrum with Kanban
Perfection Game
Lean-Agile Software Development
Introduction to ATDD
Scrum Master
LAB
Jira
predictability
Continuous Improvement
Agile Testing Practices
Agile Program
System Team
Scrum Guide
Professional Scrum Product Owner
Agile Community
Rapid RTC
GanttBan
Legacy Enterprise
Kanban 101
Code
ATDD vs. BDD
Coaching Agile Teams
chatgpt
Agile Assembly Architecture
Systems Thinking
Lean Agile
Atlassian
Kanban Game
Operational Value Stream
Agility
Accelerate Value Delivery At Scale
Scrum Values
What Is Kanban
Agile in the Enterprise
Agile Israel
SAFe Release Planning
Development Value Streams
Lean Agile Management
speed @ scale
Large Scale Scrum
Agile and DevOps Journey
Continuous Deployment
AI Artificial Intelligence
Jira Plans
System Archetypes
SAFe
Risk Management in Kanban
Agile Contracts Best Practices
Scrum Primer
Kanban Kickstart Example
Agile Project
Sprint Iteration
Acceptance Test-Driven Development
Agile Games
ALM Tools
User stories
Nexus
Business Agility
Lean Budgeting
speed at scale
DevOps
Covid19
QA
Scrum With Kanban
Webinar
Portfolio for Jira
Elastic Leadership
Continuous Planning
Test Driven Development
Value Streams
SAFe DevOps
Releases Using Lean
Applying Agile Methodology
The Agile Coach
Nexus vs SAFe
Video
Kaizen
RSA
Jira Cloud
Sprint Planning
Built-In Quality
Lean and Agile Principles and Practices
EOS®
Program Increment
Planning
Agile Exercises
SA
Software Development Estimation
Atlaassian
WIP
Nexus Integration Team
Agile Product Ownership
Certification
Scrum.org
Effective Agile Retrospectives
Team Flow
Lean Risk Management
Presentation
Slides
Product Ownership
Games and Exercises
Agile
Continuous Integration
Agile Basics
Managing Risk on Agile Projects
LeSS
Tools
Continuous Delivery
Lean Software Development
Managing Projects
Story Slicing
Lean Startup
Scrum and XP
agileisrael
Agile for Embedded Systems
AgileSparks
Tips
Agile Release Management
Software Development
Lean Agile Leadership
ARTs
Self-organization
Engineering Practices
Hybrid Work
System Integration Environments
Keith Sawyer
Agile Release Planning
PI Planning
RTE
Legacy Code
Risk-aware Product Development
Agile Israel Events
Kanban
ScrumMaster Tales
BDD
Certified SAFe
Jira admin
Reading List
Lean and Agile Techniques
Spotify
Agile Risk Management
Lean Agile Basics
Enterprise DevOps
Quality Assurance
Lean-Agile Budgeting
ART Success
Kaizen Workshop
NIT
ATDD
TDD
Scrum Master Role
Agile India
Daily Scrum
Agile Product Development
Agile Development
Artificial Intelligence
AI
Nexus and Kanban
A Kanban System for Software Engineering
POPM
Agile Delivery
Lean Agile Organization
Risk Management on Agile Projects
Implementing SAFe
LPM
Implementation of Lean and Agile
Manage Budget Creation
Introduction to Test Driven Development
Principles of Lean-Agile Leadership
Product Management
Change Management
Sprint Retrospectives
Scaled Agile Framework
RTE Role
Iterative Incremental Development
Limiting Work in Progress
Kanban Basics
Nexus and SAFe
The Kanban Method
An Appreciative Retrospective
PI Objectives
Process Improvement
Entrepreneurial Operating System®
Scrum
IT Operations
Agile Techniques
Amdocs
Achieve Business Agility
Agile Games and Exercises
Agile Marketing
SPC
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart