Scrum Board Setup Tips and Tricks

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

I’d like to share with you some tips and tricks for setting up a scrum board I usually share with my clients. The bottom line is that too many tools have too many features that support old ways of thinking. Let’s look at the various items one by one.

Subtasks

Like the human tailbone, subtasks were once useful but are now mainly a source of pain. When we worked in Waterfall we measured progress with completed subtasks, but in agile when stories are short, subtasks are a burden.

A burden for developers who need to mess with subtasks using the ALM tool.

This a burden for managers who measure progress using a burndown chart that usually relies on subtasks estimation. That’s a burden because burndown charts may time tell an incorrect story (all work done but nothing is working) – progress should be measured by “done” stories, usually a burnup chart.

Using subtasks should be a choice given to developers. If you find it useful then use it. I prefer just discussing the work to be done with the other people working with me on a story. If needed we can write it down on a whiteboard, but usually, there is no need to write it down as the story is so short. We just do the job.

Showing subtasks on a scrum board takes the focus from stories getting done to subtasks. It makes the scrum board too clattered and worse of all it lets people focus on their specific job and not on the story getting done. Bad subtasks! Bad!

Swimlanes 

Another evil thing is swimlanes. Second only to subtasks.

People usually need swimlanes because there is too much information on the board. That’s indeed a problem. Many times it will be … subtasks! If it isn’t subtasks it may be either the stories are too small or the team is too big. Or maybe something else.

The idea is we need to see why are there too many items on the board and handle that problem.

The big problem with swimlanes is that it distracts you. When you have swimlanes it is difficult to see what is now in progress. This is because usually there will be items in the “to do” column which will make the swimlane too wide to see all the items in one column.

Your focus is on the things that are now in progress and that’s what you need to see.

Many times there is a swim lane per team member. This will hint that we are trying to make sure people are utilized. Like the manifesto would say, it is important to make sure people are utilized but it is more important to get stories done.

Sometimes team members ask for a swimlane per developer. This tells us that people really care only about what they need to do and not about the team. This brings us to the next item:

Story Assignee

Almost all tools allow one person to be assigned to a story. (Leankit allows many). If you want to assign more people you can use subtasks. However, we already discussed subtasks and the conclusion was quite clear.

We will usually need to assign more than one person. In many places, at least one developer and one QA will be assigned. More than that, we will be happy if people can swarm on stories – having several people working on one story is fun and contributes to teamwork and thus very effective.

So, what do we do?

Many tools allow the addition of custom fields. For instance, Jira. I usually recommend clients working with Jira add a custom field called “assigned team members”. The field type should be multi-select. You will need to manually add the list of all team members. Once you do that you ask the tool to present the information on the card on the board and suddenly – voila! You have a strong scrum board where you see the people involved in every story. That’s great.

Last but not least – Columns

Most tools start with the standard “To Do – Doing – Done” columns + a backlog. (read here about the critical difference between backlog and to-do). That’s great! Why touch it? Please don’t.

Many teams will add a “Test” column. And a “pull request” column. And there are more.

The problem with these additional columns is that they are good excuses for things getting stuck. If there is a “dev” column and a “Test” column it means it is really all right to finish dev (I’m done!) and QA can be done later. Reminds you of subtasks? correct, it is similar.

If the sprint is only two weeks long and stories are short, there should be no reason for these additional columns. Just get done with the story – and please no stories! Remember we already have the names of all involved people on the card – just get it done with.

Conclusion

A scrum board should be very simple. There is a list of stories to do. Some are in progress, some are already done. We know who is working on what. That’s it. Don’t let fancy features distract you.

You may be interested in one of our Agile Up! workshops where we help you use popular Agile ALM tools such as Jira and TFS more effectively.

Subscribe for Email Updates:

Categories:

Tags:

Product Management
Keith Sawyer
SPC
Agile Techniques
Agile Contracts Best Practices
Risk Management on Agile Projects
Lean Startup
LAB
Agile Assembly Architecture
Program Increment
Limiting Work in Progress
Built-In Quality
Principles of Lean-Agile Leadership
Agility
Software Development
Agile Games and Exercises
Games and Exercises
Agile Israel
Change Management
Scrum Master Role
Lean Agile Organization
Agile Basics
Releases Using Lean
ATDD vs. BDD
Continuous Planning
Legacy Code
Managing Risk on Agile Projects
ART Success
AgileSparks
Tips
Agile Development
Lean Agile Management
SA
Agile Testing Practices
Kanban Basics
Sprint Planning
EOS®
Sprint Iteration
Risk-aware Product Development
Jira
Slides
NIT
Scrum
Scrum With Kanban
Lean Agile
Scaled Agile Framework
User stories
Effective Agile Retrospectives
System Archetypes
Kanban Kickstart Example
A Kanban System for Software Engineering
Introduction to Test Driven Development
Scrum Guide
DevOps
Continuous Improvement
Scrum Values
Scrum Master
Enterprise DevOps
Implementing SAFe
Engineering Practices
Covid19
Process Improvement
Continuous Integration
IT Operations
SAFe DevOps
Entrepreneurial Operating System®
Perfection Game
QA
speed at scale
Applying Agile Methodology
Nexus
Nexus vs SAFe
The Agile Coach
Lean Software Development
Manage Budget Creation
Scrum and XP
Advanced Roadmaps
Nexus Integration Team
Agile in the Enterprise
Lean and Agile Principles and Practices
Hybrid Work
Tools
Agile and DevOps Journey
BDD
Nexus and Kanban
Accelerate Value Delivery At Scale
Agile Program
Elastic Leadership
POPM
Spotify
GanttBan
Team Flow
LPM
PI Objectives
RTE Role
Risk Management in Kanban
ALM Tools
Lean Agile Leadership
Agile Product Development
Presentation
Agile Product Ownership
System Integration Environments
Lean-Agile Budgeting
Artificial Intelligence
TDD
Certified SAFe
Self-organization
Agile Marketing
Agile Israel Events
Rapid RTC
Webinar
Lean-Agile Software Development
Release Train Engineer
Lean Risk Management
Agile Release Planning
Implementation of Lean and Agile
Agile Mindset
Large Scale Scrum
Jira Plans
Kanban 101
Agile
Professional Scrum with Kanban
ATDD
System Team
Reading List
Test Driven Development
Pomodoro Technique
Jira Cloud
Story Slicing
The Kanban Method
Professional Scrum Product Owner
Agile Outsourcing
Business Agility
What Is Kanban
Agile Exercises
Agile Release Management
RSA
AI
speed @ scale
Continuous Delivery
Agile Project
Agile Games
Product Ownership
Lean Agile Basics
Iterative Incremental Development
ROI
lean agile change management
Agile for Embedded Systems
Daily Scrum
RTE
Development Value Streams
Lean and Agile Techniques
Systems Thinking
Introduction to ATDD
Frameworks
SAFe Release Planning
Sprint Retrospectives
Managing Projects
Operational Value Stream
Quality Assurance
Coaching Agile Teams
Portfolio for Jira
Continuous Deployment
Atlaassian
Agile Community
agileisrael
Achieve Business Agility
Amdocs
Scrum.org
SAFe
AI Artificial Intelligence
Legacy Enterprise
Agile Project Management
Kaizen
Kanban Game
Agile India
predictability
Professional Scrum Master
Code
Software Development Estimation
Kanban
chatgpt
WIP
Agile Delivery
Video
ScrumMaster Tales
Value Streams
Scrum Primer
ARTs
Acceptance Test-Driven Development
Certification
Jira admin
Kaizen Workshop
Nexus and SAFe
PI Planning
Lean Budgeting
Atlassian
LeSS
An Appreciative Retrospective
Agile Risk Management
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart