Iterating faster with SAFe

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

Here’s a frequently asked question in the SAFe community: I wanted to understand what SAFe says about someone who wants to go faster than 2 weeks of iteration? I mean the whole PI concept is based on 5 iterations worth of planning. What if a team/organization wants to develop and synchronize faster than 2 weeks? Is speed going to be compromised by following the standards of PI cadence?

Here’s my take:

Adjusting Cadence Length in SAFe – Can you? Should you?

SAFe considers the 2-week iteration length as a default rather than a rule.

The question you need to consider is what inspection and adaptation cycle you’re looking to accelerate – the Iteration or the PI.

Basically, do you want an opportunity to tactically adjust priorities more frequently than every 2w? Or do you want to adjust a more strategic direction more often than every 8-12w?

With the answer to that, you can experiment either with iteration length and/or PI length. Of course, the cadence length affects coordination overhead – there’s a fine balance.

Additionally, we’re talking about a Planning, Inspection, and Adaptation cadence – NOT the release cadence. Releases are on-demand meaning can be more frequent (or less).

Iteration Goals and PI Objectives provide us with room to maneuver

Another point to remember is that you can adjust iteration backlogs as long as you’re focusing on iteration goals. And even PI objectives can be adjusted – “Assume Variability Preserve Options”. If it’s occasional adjustment it’s not a reason to necessarily use a faster cadence.

Is team-level Kanban the solution to the need for more flexibility in SAFe?

Many teams think Kanban might be the best choice for them if they need more and more flexibility. Kanban CAN be a better fit if your demand is extremely volatile. I would be very careful though. Doing some level of goal-setting and prioritization and planning on a cadence is a powerful way for a team to focus. Do we really WANT to be a strictly reactive team?

Kanban combined with flexibility with some of the capacity we have each iteration can definitely be helpful and is why we recommend all Agile Teams in SAFe use Kanban to limit their WIP and improve their flow – this actually enables them to change scope even within an Iteration if that’s needed in order to achieve their Goal. (see my recent blog post that talks about dynamic scope in SAFe).

“Kanban Teams” in SAFe have an iteration cadence with the establishment of iteration goals even if not detailed iteration backlogs. Maybe that’s a good fit for your context maybe not. It might be an interesting experiment to try.

What if Planning a PI doesn’t make sense?

Finally, if PI planning doesn’t make sense even if PI is shorter – maybe you need to reflect on SAFes appropriateness for your context or on what’s so volatile about the demand coming your way and whether it’s “nature of the beast” or a systemic impediment to work on …

What’s the Bottom Line

What I tried to show here is that a conversation about what to do when the iteration feels too long should start with “Why”. Get to the bottom of what’s currently not ideal, look at the different options, consider Lean, Agile, and SAFe principles, and figure out whether it makes sense to change the cadence, change your approach to the balance between planning and flexibility, the difference between committing to goals and committing to backlogs, and the role that more flow-oriented techniques such as Kanban can play in addressing your issue.

Interested to hear any thoughts or experiences. Leave us a comment !

Subscribe for Email Updates:

Categories:

Tags:

Agile Exercises
Keith Sawyer
Value Streams
Artificial Intelligence
Spotify
Agile India
Lean Agile Basics
Lean Agile Management
Product Ownership
Applying Agile Methodology
PI Objectives
GanttBan
Lean-Agile Budgeting
Continuous Integration
Enterprise DevOps
Risk Management on Agile Projects
RTE
Acceptance Test-Driven Development
Jira admin
Kanban Basics
Releases Using Lean
Daily Scrum
Planning
Jira Cloud
Agile and DevOps Journey
Accelerate Value Delivery At Scale
Agile in the Enterprise
Agile Games
SAFe Release Planning
chatgpt
SA
Covid19
Scrum Primer
Games and Exercises
ARTs
Effective Agile Retrospectives
NIT
Webinar
Software Development
Change Management
Lean and Agile Principles and Practices
An Appreciative Retrospective
ROI
Legacy Enterprise
Continuous Deployment
BDD
Product Management
Agile Israel Events
Tips
Operational Value Stream
TDD
Introduction to Test Driven Development
Systems Thinking
AI Artificial Intelligence
Agile Marketing
System Integration Environments
Hybrid Work
Lean and Agile Techniques
What Is Kanban
speed at scale
Nexus vs SAFe
Manage Budget Creation
Entrepreneurial Operating System®
Agile Delivery
agileisrael
Pomodoro Technique
Lean Agile Leadership
Certified SAFe
DevOps
RTE Role
Agile Outsourcing
Introduction to ATDD
QA
lean agile change management
Scrum Master
Kanban 101
IT Operations
Agile Product Ownership
Video
Large Scale Scrum
RSA
LeSS
Test Driven Development
Nexus and SAFe
Scrum
Sprint Planning
System Archetypes
Tools
Continuous Delivery
LAB
Engineering Practices
Scrum Master Role
Portfolio for Jira
Atlassian
Lean Software Development
Story Slicing
Lean Risk Management
Jira
The Agile Coach
AgileSparks
Continuous Planning
Agile Program
Agile Risk Management
Scrum Values
Agile Games and Exercises
Jira Plans
Agile Mindset
Scrum With Kanban
Managing Projects
ART Success
ATDD
Self-organization
Code
Kanban Game
Professional Scrum Master
Release Train Engineer
Risk-aware Product Development
Kanban
System Team
SAFe
Coaching Agile Teams
Amdocs
Rapid RTC
Development Value Streams
Agile Contracts Best Practices
Atlaassian
Agile Product Development
Agile Project Management
Nexus and Kanban
Lean Agile Organization
ATDD vs. BDD
Lean Startup
Elastic Leadership
Reading List
Sprint Iteration
Agile
speed @ scale
Limiting Work in Progress
Kaizen
Risk Management in Kanban
LPM
WIP
AI
Principles of Lean-Agile Leadership
A Kanban System for Software Engineering
Kanban Kickstart Example
Legacy Code
Advanced Roadmaps
Business Agility
Process Improvement
Frameworks
Program Increment
Continuous Improvement
Agile Release Planning
Agile Community
Professional Scrum with Kanban
Scrum and XP
Lean Agile
Agile Development
Sprint Retrospectives
Agility
Iterative Incremental Development
User stories
SAFe DevOps
Nexus
Professional Scrum Product Owner
Team Flow
Implementation of Lean and Agile
Agile Basics
ScrumMaster Tales
Scrum Guide
Slides
Built-In Quality
Lean-Agile Software Development
Agile for Embedded Systems
EOS®
Scaled Agile Framework
Agile Techniques
Certification
Software Development Estimation
Implementing SAFe
Quality Assurance
Achieve Business Agility
Kaizen Workshop
Lean Budgeting
POPM
Perfection Game
Agile Testing Practices
Presentation
ALM Tools
Scrum.org
predictability
Nexus Integration Team
The Kanban Method
Agile Project
Agile Assembly Architecture
Managing Risk on Agile Projects
PI Planning
Agile Israel
Agile Release Management
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart