Here’s a frequently asked question in the SAFe community: I wanted to understand what SAFe says about someone who wants to go faster than 2 weeks of iteration? I mean the whole PI concept is based on 5 iterations worth of planning. What if a team/organization wants to develop and synchronize faster than 2 weeks? Is speed going to be compromised by following the standards of PI cadence?

Here’s my take:

Adjusting Cadence Length in SAFe – Can you? Should you?

SAFe considers the 2-week iteration length as a default rather than a rule.

The question you need to consider is what inspection and adaptation cycle you’re looking to accelerate – the Iteration or the PI.

Basically, do you want an opportunity to tactically adjust priorities more frequently than every 2w? Or do you want to adjust a more strategic direction more often than every 8-12w?

With the answer to that, you can experiment either with iteration length and/or PI length. Of course, the cadence length affects coordination overhead – there’s a fine balance.

Additionally, we’re talking about a Planning, Inspection, and Adaptation cadence – NOT the release cadence. Releases are on-demand meaning can be more frequent (or less).

Iteration Goals and PI Objectives provide us with room to maneuver

Another point to remember is that you can adjust iteration backlogs as long as you’re focusing on iteration goals. And even PI objectives can be adjusted – “Assume Variability Preserve Options”. If it’s occasional adjustment it’s not a reason to necessarily use a faster cadence.

Is team-level Kanban the solution to the need for more flexibility in SAFe?

Many teams think Kanban might be the best choice for them if they need more and more flexibility. Kanban CAN be a better fit if your demand is extremely volatile. I would be very careful though. Doing some level of goal-setting and prioritization and planning on a cadence is a powerful way for a team to focus. Do we really WANT to be a strictly reactive team?

Kanban combined with flexibility with some of the capacity we have each iteration can definitely be helpful and is why we recommend all Agile Teams in SAFe use Kanban to limit their WIP and improve their flow – this actually enables them to change scope even within an Iteration if that’s needed in order to achieve their Goal. (see my recent blog post that talks about dynamic scope in SAFe).

“Kanban Teams” in SAFe have an iteration cadence with the establishment of iteration goals even if not detailed iteration backlogs. Maybe that’s a good fit for your context maybe not. It might be an interesting experiment to try.

What if Planning a PI doesn’t make sense?

Finally, if PI planning doesn’t make sense even if PI is shorter – maybe you need to reflect on SAFes appropriateness for your context or on what’s so volatile about the demand coming your way and whether it’s “nature of the beast” or a systemic impediment to work on …

What’s the Bottom Line

What I tried to show here is that a conversation about what to do when the iteration feels too long should start with “Why”. Get to the bottom of what’s currently not ideal, look at the different options, consider Lean, Agile, and SAFe principles, and figure out whether it makes sense to change the cadence, change your approach to the balance between planning and flexibility, the difference between committing to goals and committing to backlogs, and the role that more flow-oriented techniques such as Kanban can play in addressing your issue.

Interested to hear any thoughts or experiences. Leave us a comment !

Categories:

Tags:

Implementing SAFe
Managing Projects
PI Planning
Risk-aware Product Development
Operational Value Stream
ALM Tools
LPM
Nexus and Kanban
Lean-Agile Software Development
Sprint Retrospectives
Applying Agile Methodology
Agile Outsourcing
Sprint Planning
Introduction to ATDD
Software Development
AI Artificial Intelligence
Scrum and XP
Kanban Basics
Artificial Intelligence
Kanban 101
Spotify
Continuous Delivery
Professional Scrum with Kanban
Story Slicing
Systems Thinking
Games and Exercises
Lean Software Development
Jira Plans
Agile Basics
Agile Techniques
Agile
Portfolio for Jira
Iterative Incremental Development
System Archetypes
QA
LAB
Effective Agile Retrospectives
Tips
Introduction to Test Driven Development
What Is Kanban
Amdocs
Presentation
Agile Release Planning
Daily Scrum
Large Scale Scrum
BDD
Reading List
Lean Risk Management
Perfection Game
SAFe
Business Agility
Legacy Enterprise
Lean and Agile Techniques
Nexus vs SAFe
Elastic Leadership
Jira Cloud
Agile Community
Nexus Integration Team
A Kanban System for Software Engineering
Webinar
Kanban
Nexus
Scrum With Kanban
Continuous Integration
Implementation of Lean and Agile
ARTs
Lean Agile Leadership
Acceptance Test-Driven Development
ROI
Release Train Engineer
Risk Management on Agile Projects
Scrum Primer
SPC
Scrum Master
Agile Testing Practices
System Integration Environments
Engineering Practices
Agile Assembly Architecture
Lean-Agile Budgeting
RSA
Agile India
Continuous Deployment
Enterprise DevOps
Manage Budget Creation
The Agile Coach
GanttBan
Principles of Lean-Agile Leadership
speed @ scale
Accelerate Value Delivery At Scale
Self-organization
Agile Development
Kanban Game
Continuous Improvement
Kaizen Workshop
Agile Games
Video
POPM
Value Streams
Agile Product Development
Coaching Agile Teams
Legacy Code
SAFe DevOps
PI Objectives
RTE
Agile Program
Scrum Values
RTE Role
An Appreciative Retrospective
Agile and DevOps Journey
Program Increment
Advanced Roadmaps
Agile Project
Agile Delivery
Limiting Work in Progress
Agile Games and Exercises
Test Driven Development
Agility
Agile Risk Management
SA
ART Success
lean agile change management
Sprint Iteration
ATDD
Scrum
speed at scale
Professional Scrum Master
Lean and Agile Principles and Practices
Entrepreneurial Operating System®
Atlaassian
Development Value Streams
WIP
Agile Product Ownership
Agile Release Management
Scaled Agile Framework
Product Ownership
Built-In Quality
Change Management
Frameworks
SAFe Release Planning
Continuous Planning
Releases Using Lean
Scrum Guide
Risk Management in Kanban
DevOps
Jira
Rapid RTC
Nexus and SAFe
Hybrid Work
Managing Risk on Agile Projects
Agile for Embedded Systems
Lean Startup
ATDD vs. BDD
Certification
Professional Scrum Product Owner
Agile Project Management
ScrumMaster Tales
Lean Agile
Certified SAFe
LeSS
Lean Budgeting
Product Management
Scrum Master Role
Slides
Agile Mindset
Code
Kanban Kickstart Example
Pomodoro Technique
Agile Exercises
Agile Marketing
Achieve Business Agility
Agile in the Enterprise
Planning
Software Development Estimation
NIT
AgileSparks
EOS®
Kaizen
Lean Agile Basics
Lean Agile Management
Lean Agile Organization
Agile Israel Events
TDD
IT Operations
Process Improvement
The Kanban Method
System Team
Quality Assurance
Covid19
Scrum.org
AgileSparks
Logo

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart