Iterating faster with SAFe

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

Here’s a frequently asked question in the SAFe community: I wanted to understand what SAFe says about someone who wants to go faster than 2 weeks of iteration? I mean the whole PI concept is based on 5 iterations worth of planning. What if a team/organization wants to develop and synchronize faster than 2 weeks? Is speed going to be compromised by following the standards of PI cadence?

Here’s my take:

Adjusting Cadence Length in SAFe – Can you? Should you?

SAFe considers the 2-week iteration length as a default rather than a rule.

The question you need to consider is what inspection and adaptation cycle you’re looking to accelerate – the Iteration or the PI.

Basically, do you want an opportunity to tactically adjust priorities more frequently than every 2w? Or do you want to adjust a more strategic direction more often than every 8-12w?

With the answer to that, you can experiment either with iteration length and/or PI length. Of course, the cadence length affects coordination overhead – there’s a fine balance.

Additionally, we’re talking about a Planning, Inspection, and Adaptation cadence – NOT the release cadence. Releases are on-demand meaning can be more frequent (or less).

Iteration Goals and PI Objectives provide us with room to maneuver

Another point to remember is that you can adjust iteration backlogs as long as you’re focusing on iteration goals. And even PI objectives can be adjusted – “Assume Variability Preserve Options”. If it’s occasional adjustment it’s not a reason to necessarily use a faster cadence.

Is team-level Kanban the solution to the need for more flexibility in SAFe?

Many teams think Kanban might be the best choice for them if they need more and more flexibility. Kanban CAN be a better fit if your demand is extremely volatile. I would be very careful though. Doing some level of goal-setting and prioritization and planning on a cadence is a powerful way for a team to focus. Do we really WANT to be a strictly reactive team?

Kanban combined with flexibility with some of the capacity we have each iteration can definitely be helpful and is why we recommend all Agile Teams in SAFe use Kanban to limit their WIP and improve their flow – this actually enables them to change scope even within an Iteration if that’s needed in order to achieve their Goal. (see my recent blog post that talks about dynamic scope in SAFe).

“Kanban Teams” in SAFe have an iteration cadence with the establishment of iteration goals even if not detailed iteration backlogs. Maybe that’s a good fit for your context maybe not. It might be an interesting experiment to try.

What if Planning a PI doesn’t make sense?

Finally, if PI planning doesn’t make sense even if PI is shorter – maybe you need to reflect on SAFes appropriateness for your context or on what’s so volatile about the demand coming your way and whether it’s “nature of the beast” or a systemic impediment to work on …

What’s the Bottom Line

What I tried to show here is that a conversation about what to do when the iteration feels too long should start with “Why”. Get to the bottom of what’s currently not ideal, look at the different options, consider Lean, Agile, and SAFe principles, and figure out whether it makes sense to change the cadence, change your approach to the balance between planning and flexibility, the difference between committing to goals and committing to backlogs, and the role that more flow-oriented techniques such as Kanban can play in addressing your issue.

Interested to hear any thoughts or experiences. Leave us a comment !

Subscribe for Email Updates:

Categories:

Tags:

Continuous Delivery
Agile India
Sprint Planning
SPC
Quality Assurance
Scrum With Kanban
Agile Techniques
Risk-aware Product Development
agileisrael
Artificial Intelligence
Amdocs
Achieve Business Agility
Scrum
System Team
ATDD vs. BDD
Change Management
Agile Community
Sprint Retrospectives
Continuous Improvement
Principles of Lean-Agile Leadership
Enterprise DevOps
Lean Agile Management
SAFe
Nexus and SAFe
Lean Risk Management
PI Objectives
Agile Contracts Best Practices
Agile Release Management
Process Improvement
Agile Risk Management
RTE Role
Agile Exercises
Implementation of Lean and Agile
LAB
Software Development Estimation
Legacy Code
PI Planning
Kanban Basics
Agile Basics
Agility
Atlaassian
Lean Agile Organization
Pomodoro Technique
Agile Product Development
Kanban 101
System Archetypes
Product Ownership
Managing Risk on Agile Projects
Tips
Agile for Embedded Systems
RTE
ART Success
Scaled Agile Framework
Team Flow
Portfolio for Jira
TDD
Nexus and Kanban
Value Streams
ARTs
Certification
Lean Agile
Lean-Agile Budgeting
Releases Using Lean
Agile Project
Lean Startup
Story Slicing
AgileSparks
Agile Games
speed @ scale
Scrum Values
Tools
Agile Release Planning
Effective Agile Retrospectives
Continuous Deployment
Agile Israel
Risk Management in Kanban
SAFe DevOps
RSA
Presentation
Scrum Master
Risk Management on Agile Projects
Scrum Guide
Agile Program
Covid19
An Appreciative Retrospective
Agile in the Enterprise
Agile Outsourcing
Video
Nexus vs SAFe
LeSS
Agile Assembly Architecture
Agile Israel Events
Operational Value Stream
Reading List
Keith Sawyer
Lean and Agile Principles and Practices
Elastic Leadership
Kaizen Workshop
Atlassian
Lean Budgeting
lean agile change management
Certified SAFe
Kanban Kickstart Example
Development Value Streams
Agile Product Ownership
Agile Delivery
Slides
A Kanban System for Software Engineering
Spotify
Implementing SAFe
Perfection Game
Agile Project Management
The Agile Coach
Professional Scrum Master
Agile Games and Exercises
WIP
Built-In Quality
Engineering Practices
Manage Budget Creation
Coaching Agile Teams
Business Agility
QA
The Kanban Method
Scrum Primer
AI Artificial Intelligence
Lean and Agile Techniques
Lean Software Development
Nexus
Iterative Incremental Development
Agile Mindset
ATDD
Agile and DevOps Journey
Legacy Enterprise
Webinar
Accelerate Value Delivery At Scale
Jira Cloud
Release Train Engineer
Professional Scrum with Kanban
Large Scale Scrum
Continuous Planning
Agile Development
What Is Kanban
Lean Agile Basics
Product Management
Hybrid Work
Sprint Iteration
Nexus Integration Team
Acceptance Test-Driven Development
SA
Continuous Integration
predictability
Daily Scrum
Jira
Systems Thinking
SAFe Release Planning
Professional Scrum Product Owner
Lean Agile Leadership
IT Operations
Frameworks
AI
Applying Agile Methodology
System Integration Environments
Program Increment
Managing Projects
Advanced Roadmaps
Kanban
Test Driven Development
Introduction to Test Driven Development
chatgpt
Entrepreneurial Operating System®
Games and Exercises
BDD
Agile Testing Practices
Scrum Master Role
Kaizen
EOS®
Limiting Work in Progress
Scrum and XP
Jira Plans
Agile
Agile Marketing
speed at scale
ALM Tools
Scrum.org
NIT
Code
Software Development
Planning
POPM
Kanban Game
ROI
GanttBan
Self-organization
DevOps
ScrumMaster Tales
Lean-Agile Software Development
User stories
Rapid RTC
Introduction to ATDD
Jira admin
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart