Limiting Work in Progress (WIP) – some anecdotes worth thinking about when using Kanban with Scrum

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

Co-Creating and teaching the new Scrum.org Professional Scrum with Kanban class has given me an opportunity to get back to geeking out on WIP limits, flow metrics, and all things Kanban. And it’s been fun!

One of the key Kanban practices is Limiting Work in Progress. If you want to be pedantic, actually what this practice aims for is Reducing and stabilizing Work in Progress. This improves flow, provides predictability, and is actually even more important for creating a pull-based Kanban system than visualizing your workflow using a Kanban board. I worked with several clients who limited their WIP but didn’t use Kanban boards. One could argue that maybe this practice deserves to be first in the list of Kanban practices, ahead of Visualization.

Anyhow, when a Scrum Team implements Kanban they should definitely figure out how to limit and reduce their Work in Progress. This is a key part of their definition of “Workflow”. First of all, when we say flow we mean flow of valuable items – so flow of PBIs (rather than tasks).

Now, a question comes up: Who should define the WIP Limit? Let’s assume the team is using Kanban to improve the Sprint flow by visualizing and managing flow in the Sprint Backlog. Sprint Backlog is owned by the Development Team so it would make sense for them to own their workflow and specifically the WIP limits in this case.

What if the team is using Kanban from a more holistic perspective, starting from the Product Backlog and including refinement work as well? In this case, it would be the Scrum Team that would own the workflow and therefore would need to discuss WIP limits.

Now, what if the Dev Team actually wants to involve the Product Owner in their Sprint flow – e.g. to review and accept a story during the Sprint before it goes through testing? Who decides whether to do this? Who owns the Sprint Backlog in this case? I think it is the Scrum Team.

Ok, so we understand who defines workflow and therefore WIP limits. Now let’s assume a team is mid-Sprint and there’s an important valuable item the Product Owner wants to add to the Sprint Backlog. It is aligned with the Sprint Goal. The team is currently at its WIP Limit. Could they add this item? Should they? What needs to happen to the WIP limit?

My take on this is that first of all a decision needs to be made on whether to pull this item into the Sprint Backlog. This discussion isn’t related to Kanban at all. It is a core Scrum question and the answer is that it is up to the team to agree to pull a new item into the Sprint Backlog. The Sprint Goal can be used to assess how aligned this item is with the current focus.

In case the item is pulled into the Sprint Backlog, then the Dev Team needs to figure out whether they can actually start it right away. This depends on the WIP limits and the current WIP. If the team is at their WIP they shouldn’t pull in that new item until some room frees up. If their backlog items are pretty small, an empty WIP slot will free up pretty quickly. If items are big, it can take a while.

The longer it might take to get a normal pull slot ready, the more pressure there might be to actually expedite this card. What is expediting? going beyond the current WIP limits and pushing this item along on top of the existing flow. The typical way to do this is NOT to change the WIP limit definition but to go above WIP and note a WIP exception. These exceptions can then be a topic for inspection and adaptation come time to retrospect.

In general, I don’t recommend changing WIP limits on a whim just because there seems to be a need during the Sprint. I’d rather see an exception and discussion rather than hide the problem under a policy change. Most of the time, Scrum Teams should adjust WIP limits during the Sprint Retrospective out of an attempt to create a better flow strategy, not a way to manage at the tactical level. This is similar to the definition of Done. We don’t change the definition of Done during a sprint just because we have a problem creating a Done Increment. We note the exception, maybe even fail to create a really Done Increment, and we discuss the definition during our Retrospective.

One last thing to note about limiting WIP is that while we typically talk about limiting WIP as per-lane constraints on your workflow, this is actually just one specific way to do it. You could limit the amount of work in progress per person, per the entire team throughout their workflow, or actually, you could limit WIP by time. E.g. “we won’t work on more than 10 items this week”. Hey – that sounds familiar! #SprintForecast.

NOTE: Updated to emphasize that we want to limit WIP by valuable PBIs (rather than tasks). Thanks, Giora for suggesting to make that explicit.

Subscribe for Email Updates:

Categories:

Tags:

Continuous Improvement
LeSS
Release Train Engineer
Certified SAFe
chatgpt
Agile Israel Events
Scrum and XP
Lean-Agile Budgeting
Effective Agile Retrospectives
Agile Basics
Pomodoro Technique
PI Planning
Artificial Intelligence
Lean-Agile Software Development
Software Development Estimation
Jira
RSA
Kanban Basics
Agile Marketing
Risk Management on Agile Projects
Sprint Iteration
Jira Cloud
ART Success
lean agile change management
NIT
Agile Techniques
Achieve Business Agility
predictability
Program Increment
AI
Lean Risk Management
Agile Exercises
Large Scale Scrum
Business Agility
ATDD vs. BDD
Managing Projects
RTE
Iterative Incremental Development
Continuous Delivery
Lean Agile Organization
Kanban 101
ALM Tools
Agile Testing Practices
ARTs
Legacy Enterprise
Agile Development
Agile Project
Agile Outsourcing
Agile for Embedded Systems
Agile and DevOps Journey
Games and Exercises
Entrepreneurial Operating System®
Reading List
Planning
Daily Scrum
Frameworks
Professional Scrum Master
Elastic Leadership
The Agile Coach
Jira Plans
Scrum Master Role
Agile Release Planning
Keith Sawyer
Scrum Master
Lean and Agile Techniques
Agile Games
Kaizen Workshop
Agile Contracts Best Practices
System Integration Environments
Nexus Integration Team
Releases Using Lean
Operational Value Stream
Covid19
Kaizen
Agile
LPM
A Kanban System for Software Engineering
Agile Project Management
PI Objectives
Limiting Work in Progress
Scrum
What Is Kanban
Lean and Agile Principles and Practices
Enterprise DevOps
Product Management
Principles of Lean-Agile Leadership
Certification
Atlassian
Agile Delivery
Continuous Integration
Agile Product Ownership
Product Ownership
Development Value Streams
Tips
Tools
Lean Startup
Agile Community
SPC
TDD
LAB
Agility
Professional Scrum Product Owner
Implementing SAFe
Code
ATDD
Scaled Agile Framework
IT Operations
Test Driven Development
Nexus and SAFe
Engineering Practices
SAFe
The Kanban Method
Lean Agile Management
Webinar
Kanban Kickstart Example
Sprint Planning
Coaching Agile Teams
Lean Software Development
Amdocs
Value Streams
Agile Program
Agile Risk Management
Agile Product Development
Lean Agile Basics
ScrumMaster Tales
Spotify
Quality Assurance
Slides
Video
Nexus
SA
Advanced Roadmaps
Story Slicing
Introduction to Test Driven Development
Presentation
WIP
Process Improvement
Atlaassian
Sprint Retrospectives
Continuous Deployment
Self-organization
Scrum Values
Kanban Game
Risk-aware Product Development
Manage Budget Creation
An Appreciative Retrospective
Systems Thinking
SAFe Release Planning
Scrum.org
Kanban
agileisrael
Lean Budgeting
Built-In Quality
Agile Release Management
AgileSparks
System Team
Scrum Primer
speed at scale
Risk Management in Kanban
POPM
Introduction to ATDD
ROI
Hybrid Work
System Archetypes
Agile Mindset
Team Flow
Acceptance Test-Driven Development
Nexus vs SAFe
Scrum With Kanban
RTE Role
Accelerate Value Delivery At Scale
Agile Israel
speed @ scale
Scrum Guide
EOS®
Nexus and Kanban
Lean Agile
Change Management
DevOps
Lean Agile Leadership
Jira admin
Agile in the Enterprise
Agile India
AI Artificial Intelligence
GanttBan
Agile Assembly Architecture
SAFe DevOps
Perfection Game
Continuous Planning
BDD
Agile Games and Exercises
Software Development
Rapid RTC
Implementation of Lean and Agile
Applying Agile Methodology
Managing Risk on Agile Projects
Portfolio for Jira
Legacy Code
QA
Professional Scrum with Kanban
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart