Limiting Work in Progress (WIP) – some anecdotes worth thinking about when using Kanban with Scrum

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

Co-Creating and teaching the new Scrum.org Professional Scrum with Kanban class has given me an opportunity to get back to geeking out on WIP limits, flow metrics, and all things Kanban. And it’s been fun!

One of the key Kanban practices is Limiting Work in Progress. If you want to be pedantic, actually what this practice aims for is Reducing and stabilizing Work in Progress. This improves flow, provides predictability, and is actually even more important for creating a pull-based Kanban system than visualizing your workflow using a Kanban board. I worked with several clients who limited their WIP but didn’t use Kanban boards. One could argue that maybe this practice deserves to be first in the list of Kanban practices, ahead of Visualization.

Anyhow, when a Scrum Team implements Kanban they should definitely figure out how to limit and reduce their Work in Progress. This is a key part of their definition of “Workflow”. First of all, when we say flow we mean flow of valuable items – so flow of PBIs (rather than tasks).

Now, a question comes up: Who should define the WIP Limit? Let’s assume the team is using Kanban to improve the Sprint flow by visualizing and managing flow in the Sprint Backlog. Sprint Backlog is owned by the Development Team so it would make sense for them to own their workflow and specifically the WIP limits in this case.

What if the team is using Kanban from a more holistic perspective, starting from the Product Backlog and including refinement work as well? In this case, it would be the Scrum Team that would own the workflow and therefore would need to discuss WIP limits.

Now, what if the Dev Team actually wants to involve the Product Owner in their Sprint flow – e.g. to review and accept a story during the Sprint before it goes through testing? Who decides whether to do this? Who owns the Sprint Backlog in this case? I think it is the Scrum Team.

Ok, so we understand who defines workflow and therefore WIP limits. Now let’s assume a team is mid-Sprint and there’s an important valuable item the Product Owner wants to add to the Sprint Backlog. It is aligned with the Sprint Goal. The team is currently at its WIP Limit. Could they add this item? Should they? What needs to happen to the WIP limit?

My take on this is that first of all a decision needs to be made on whether to pull this item into the Sprint Backlog. This discussion isn’t related to Kanban at all. It is a core Scrum question and the answer is that it is up to the team to agree to pull a new item into the Sprint Backlog. The Sprint Goal can be used to assess how aligned this item is with the current focus.

In case the item is pulled into the Sprint Backlog, then the Dev Team needs to figure out whether they can actually start it right away. This depends on the WIP limits and the current WIP. If the team is at their WIP they shouldn’t pull in that new item until some room frees up. If their backlog items are pretty small, an empty WIP slot will free up pretty quickly. If items are big, it can take a while.

The longer it might take to get a normal pull slot ready, the more pressure there might be to actually expedite this card. What is expediting? going beyond the current WIP limits and pushing this item along on top of the existing flow. The typical way to do this is NOT to change the WIP limit definition but to go above WIP and note a WIP exception. These exceptions can then be a topic for inspection and adaptation come time to retrospect.

In general, I don’t recommend changing WIP limits on a whim just because there seems to be a need during the Sprint. I’d rather see an exception and discussion rather than hide the problem under a policy change. Most of the time, Scrum Teams should adjust WIP limits during the Sprint Retrospective out of an attempt to create a better flow strategy, not a way to manage at the tactical level. This is similar to the definition of Done. We don’t change the definition of Done during a sprint just because we have a problem creating a Done Increment. We note the exception, maybe even fail to create a really Done Increment, and we discuss the definition during our Retrospective.

One last thing to note about limiting WIP is that while we typically talk about limiting WIP as per-lane constraints on your workflow, this is actually just one specific way to do it. You could limit the amount of work in progress per person, per the entire team throughout their workflow, or actually, you could limit WIP by time. E.g. “we won’t work on more than 10 items this week”. Hey – that sounds familiar! #SprintForecast.

NOTE: Updated to emphasize that we want to limit WIP by valuable PBIs (rather than tasks). Thanks, Giora for suggesting to make that explicit.

Subscribe for Email Updates:

Categories:

Tags:

Systems Thinking
Kaizen Workshop
Releases Using Lean
Agile Testing Practices
Agile Exercises
A Kanban System for Software Engineering
Kanban
IT Operations
SAFe DevOps
Planning
Agile Project Management
Limiting Work in Progress
Jira
Nexus
TDD
What Is Kanban
Jira admin
Process Improvement
Professional Scrum Master
System Integration Environments
Amdocs
Agile Techniques
Lean Agile Management
ATDD
Presentation
Certification
Agile in the Enterprise
Scrum and XP
SPC
POPM
Enterprise DevOps
Professional Scrum Product Owner
Agile Product Development
Agile Release Planning
Portfolio for Jira
Agile Basics
Atlaassian
Covid19
Change Management
Lean and Agile Principles and Practices
Manage Budget Creation
Implementing SAFe
Sprint Iteration
Applying Agile Methodology
Lean-Agile Software Development
Agile Games
Kanban Basics
Scrum
Lean Agile Organization
Tools
Elastic Leadership
AI
Scrum Primer
Sprint Retrospectives
User stories
Artificial Intelligence
Scrum.org
Agility
QA
Agile Assembly Architecture
Risk-aware Product Development
Legacy Enterprise
The Kanban Method
Continuous Delivery
Frameworks
Lean Agile Leadership
Agile Project
Scaled Agile Framework
Quality Assurance
Principles of Lean-Agile Leadership
Jira Cloud
Legacy Code
Continuous Planning
chatgpt
Video
Certified SAFe
PI Planning
Lean Software Development
Story Slicing
Program Increment
Development Value Streams
Agile Mindset
Agile Product Ownership
Nexus and Kanban
EOS®
Perfection Game
Advanced Roadmaps
Agile Delivery
Risk Management on Agile Projects
Agile for Embedded Systems
GanttBan
Risk Management in Kanban
Introduction to ATDD
SAFe Release Planning
Self-organization
Kaizen
Continuous Improvement
ROI
Engineering Practices
Iterative Incremental Development
Agile Israel Events
Agile Release Management
Professional Scrum with Kanban
RSA
Value Streams
Kanban 101
ARTs
DevOps
Business Agility
Agile and DevOps Journey
PI Objectives
Agile Program
LeSS
Pomodoro Technique
ART Success
Jira Plans
Agile Risk Management
Acceptance Test-Driven Development
BDD
AgileSparks
speed at scale
Scrum Values
LAB
Achieve Business Agility
RTE
WIP
SA
Nexus and SAFe
ALM Tools
agileisrael
Scrum Master Role
Managing Projects
Agile Development
Software Development
NIT
Scrum Guide
Software Development Estimation
Implementation of Lean and Agile
SAFe
Sprint Planning
LPM
Scrum With Kanban
Atlassian
Rapid RTC
Coaching Agile Teams
lean agile change management
Lean Agile
Entrepreneurial Operating System®
Code
Agile Games and Exercises
Agile India
Agile Marketing
Nexus vs SAFe
System Team
Tips
Agile
ScrumMaster Tales
Agile Community
Operational Value Stream
predictability
Reading List
Webinar
The Agile Coach
Lean Startup
Spotify
Hybrid Work
ATDD vs. BDD
Daily Scrum
Nexus Integration Team
Lean Agile Basics
Scrum Master
Keith Sawyer
speed @ scale
Accelerate Value Delivery At Scale
Built-In Quality
Effective Agile Retrospectives
Games and Exercises
Continuous Deployment
Lean and Agile Techniques
Slides
Product Management
Agile Outsourcing
Managing Risk on Agile Projects
An Appreciative Retrospective
Kanban Kickstart Example
Team Flow
Product Ownership
Test Driven Development
Kanban Game
Lean Budgeting
Continuous Integration
Agile Israel
Introduction to Test Driven Development
Large Scale Scrum
Lean Risk Management
Lean-Agile Budgeting
RTE Role
System Archetypes
AI Artificial Intelligence
Release Train Engineer
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart