PI Planning Magic!

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

Intro

Earlier this month I was helping a software organization in an Israeli defense organization (that’s why there are no pictures) run their first PI Planning event. The day after I told my colleagues at Agilesparks that this is one event I will try to remember whenever I get into difficult times doing coaching, something that happens from time to time, coaching being what it is. I will try to remember that day because of the magic that happened somewhere around noon. And I want to tell you all about it.

If you aren’t familiar with it, PI Planning is an event where the entire (yes, entire) organization (or part of the organization, if it is big, up to around 125 people) convenes for 2 days to plan the next 4 to 6 iterations (sprints). Most people, hearing about it for the first time, respond in the exact way you did just now – incredulity. Yet, at the end of the event people are just talking about how will they make the next time even better. Having said that, the event we did this time was one day only – you need to choose your battles. As you will see, we needed that extra time.

Warm-up

The main purpose of the PI Planning event is to align and synchronize the organization and so the first day opens with overviews by various stakeholders, product managers and architects, all bringing concise messages and information – we don’t want all the people sitting there getting too bored, a challenging task. Immediately following this the teams break out for planning. Everyone stays in the same venue, huddling around tables, trying to come up with content for each of the PI’s iterations (leaving the last iteration for other things.) And here things start to warm up.

At the beginning the teams will usually stay together, calculating their capacity for each iteration and better understanding the required features to develop. However, after an hour or so it starts to be evident that there are dependencies on other teams, and this is exactly what happened at the mentioned event. One of the reasons the organization went into this in the first place is that coordination and alignment between teams did not fare so well. Yet, even though it was obvious the dependencies should be discussed, teams preferred to continue and look at their own plans, keeping to their tables, exactly like other teams in other organizations do.

Enter the program board

This is a good time to mention that another output of the event, in addition to the team’s plan, is the program board on which we clearly see dependencies between the teams. At this point of the event, the board was empty. Seeing the situation for what it was, the RTE, a sort of a scrum master of the scrum teams, started going around the tables, prompting people to start placing dependencies on the board, assertively. And so they did. And then magic happened.

We asked teams that placed dependencies on the board to make sure they talk about it with the relevant teams (people and interactions over processes and tools, right?) and this started an interaction across the teams. While at the beginning the noticeable huddle was around the program board, soon you started to see people from different teams at other teams’ tables. It was not just scrum master to scrum master but any representative with any other team members. People were thinking about where should they move this story and whether they could split that feature to accommodate for the dependencies. Suddenly you saw how decision-making went down to the ranks, how they took ownership of the big plan.

Self Organization Magic

That magic of self-organization was happening right before our eyes. Instead of some managers making all the decisions and being the pipelines for messages, people were interacting directly. Later the RTE said that while she felt she was a bit losing control of the happenings, the volume of interactions and decisions was something that couldn’t be tracked by one person. She was happy.

At some point it seemed as though energy is starting to go down and that we can start to wrap up. The RTE called for a scrum of scrum meeting around the program board where some dependencies were not handled. We gave the teams another 45 minutes.

The Confidence Vote

Once we had everyone’s attention – it was not an easy task – we asked the people to raise their hands in the air and indicate with the number of fingers what is their level of confidence in the plan. One means no confidence at all, and five means excellent. As hands went up in the air we saw one One and a few Twos. Most were from one team. We asked the people what was the issue and the response we got was that everything got into the plan because this is what they were asked to do. Not good.

What the RTE did at this point was to allocate another 30 minutes for the teams to change their plans so they will believe in them. Stories were moved, features got a bit thinner and when we had the vote again, we had a few Threes and the rest were Fours and Fives. The number of Threes was small enough for us to decide to handle these issues during execution.

Retrospective

At the very end of the day, we asked the teams to present the main findings of their retrospective. The feedback was good, mainly that teams agreed on them when and who will do what is something that so far they couldn’t manage to do. This fast coordination loop is making things that would usually take weeks or months to happen in one day. And that’s magic!

Subscribe for Email Updates:

Categories:

Tags:

Change Management
Built-In Quality
Artificial Intelligence
NIT
Kanban Basics
Presentation
ScrumMaster Tales
Lean-Agile Software Development
System Integration Environments
Jira Cloud
DevOps
TDD
Agile Contracts Best Practices
lean agile change management
User stories
Agile Product Development
Agile Delivery
Scrum Master
Agile
Professional Scrum Product Owner
Agile Israel
SPC
BDD
Introduction to Test Driven Development
Release Train Engineer
Lean Agile Management
Agile Product Ownership
ROI
An Appreciative Retrospective
Nexus and SAFe
Agile Release Planning
Keith Sawyer
Jira Plans
Agile Testing Practices
Managing Projects
System Archetypes
Agile Assembly Architecture
IT Operations
Kaizen Workshop
Team Flow
Story Slicing
Jira
GanttBan
Agile Development
Planning
Video
Acceptance Test-Driven Development
AgileSparks
Agile Community
speed @ scale
Agility
POPM
Atlassian
Kanban Game
Releases Using Lean
Value Streams
Agile Games
Agile Israel Events
Pomodoro Technique
Kanban 101
ATDD vs. BDD
Agile Basics
Quality Assurance
Perfection Game
Operational Value Stream
Engineering Practices
Scrum Guide
Scrum.org
Continuous Deployment
LAB
SAFe DevOps
Agile Games and Exercises
Risk Management in Kanban
Professional Scrum Master
SA
Nexus Integration Team
Certification
ARTs
Tools
RTE Role
PI Objectives
Nexus
Games and Exercises
Process Improvement
speed at scale
Agile Project Management
EOS®
LeSS
Scrum With Kanban
Spotify
AI Artificial Intelligence
AI
Lean Startup
Implementation of Lean and Agile
Development Value Streams
Lean Budgeting
Product Ownership
Sprint Iteration
Legacy Code
What Is Kanban
Lean Agile
Agile Risk Management
System Team
Scrum
Agile Release Management
Kanban Kickstart Example
ALM Tools
Coaching Agile Teams
Scaled Agile Framework
A Kanban System for Software Engineering
Introduction to ATDD
LPM
Test Driven Development
Iterative Incremental Development
Managing Risk on Agile Projects
Agile Mindset
Lean Agile Organization
Elastic Leadership
Lean Agile Leadership
Accelerate Value Delivery At Scale
Scrum Values
SAFe
Software Development Estimation
Enterprise DevOps
Legacy Enterprise
Agile for Embedded Systems
Program Increment
Continuous Integration
Portfolio for Jira
Agile in the Enterprise
Sprint Planning
Professional Scrum with Kanban
Certified SAFe
Lean Agile Basics
PI Planning
RTE
Kanban
Entrepreneurial Operating System®
Self-organization
Continuous Planning
Agile Techniques
Software Development
Atlaassian
Agile Project
Scrum Master Role
Advanced Roadmaps
QA
chatgpt
Implementing SAFe
Effective Agile Retrospectives
The Agile Coach
Lean and Agile Principles and Practices
Webinar
Continuous Improvement
ART Success
Systems Thinking
Risk-aware Product Development
Agile Program
Kaizen
Agile and DevOps Journey
Frameworks
SAFe Release Planning
Sprint Retrospectives
Limiting Work in Progress
Lean-Agile Budgeting
Covid19
Principles of Lean-Agile Leadership
Agile Marketing
Scrum and XP
Nexus vs SAFe
RSA
Scrum Primer
Lean Software Development
Continuous Delivery
Achieve Business Agility
Manage Budget Creation
predictability
Agile Exercises
WIP
Tips
Amdocs
Large Scale Scrum
Lean and Agile Techniques
Agile India
The Kanban Method
Reading List
Product Management
Daily Scrum
Rapid RTC
Nexus and Kanban
Code
Agile Outsourcing
Risk Management on Agile Projects
Business Agility
Jira admin
ATDD
agileisrael
Lean Risk Management
Hybrid Work
Slides
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart