PI Planning Magic!

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

Intro

Earlier this month I was helping a software organization in an Israeli defense organization (that’s why there are no pictures) run their first PI Planning event. The day after I told my colleagues at Agilesparks that this is one event I will try to remember whenever I get into difficult times doing coaching, something that happens from time to time, coaching being what it is. I will try to remember that day because of the magic that happened somewhere around noon. And I want to tell you all about it.

If you aren’t familiar with it, PI Planning is an event where the entire (yes, entire) organization (or part of the organization, if it is big, up to around 125 people) convenes for 2 days to plan the next 4 to 6 iterations (sprints). Most people, hearing about it for the first time, respond in the exact way you did just now – incredulity. Yet, at the end of the event people are just talking about how will they make the next time even better. Having said that, the event we did this time was one day only – you need to choose your battles. As you will see, we needed that extra time.

Warm-up

The main purpose of the PI Planning event is to align and synchronize the organization and so the first day opens with overviews by various stakeholders, product managers and architects, all bringing concise messages and information – we don’t want all the people sitting there getting too bored, a challenging task. Immediately following this the teams break out for planning. Everyone stays in the same venue, huddling around tables, trying to come up with content for each of the PI’s iterations (leaving the last iteration for other things.) And here things start to warm up.

At the beginning the teams will usually stay together, calculating their capacity for each iteration and better understanding the required features to develop. However, after an hour or so it starts to be evident that there are dependencies on other teams, and this is exactly what happened at the mentioned event. One of the reasons the organization went into this in the first place is that coordination and alignment between teams did not fare so well. Yet, even though it was obvious the dependencies should be discussed, teams preferred to continue and look at their own plans, keeping to their tables, exactly like other teams in other organizations do.

Enter the program board

This is a good time to mention that another output of the event, in addition to the team’s plan, is the program board on which we clearly see dependencies between the teams. At this point of the event, the board was empty. Seeing the situation for what it was, the RTE, a sort of a scrum master of the scrum teams, started going around the tables, prompting people to start placing dependencies on the board, assertively. And so they did. And then magic happened.

We asked teams that placed dependencies on the board to make sure they talk about it with the relevant teams (people and interactions over processes and tools, right?) and this started an interaction across the teams. While at the beginning the noticeable huddle was around the program board, soon you started to see people from different teams at other teams’ tables. It was not just scrum master to scrum master but any representative with any other team members. People were thinking about where should they move this story and whether they could split that feature to accommodate for the dependencies. Suddenly you saw how decision-making went down to the ranks, how they took ownership of the big plan.

Self Organization Magic

That magic of self-organization was happening right before our eyes. Instead of some managers making all the decisions and being the pipelines for messages, people were interacting directly. Later the RTE said that while she felt she was a bit losing control of the happenings, the volume of interactions and decisions was something that couldn’t be tracked by one person. She was happy.

At some point it seemed as though energy is starting to go down and that we can start to wrap up. The RTE called for a scrum of scrum meeting around the program board where some dependencies were not handled. We gave the teams another 45 minutes.

The Confidence Vote

Once we had everyone’s attention – it was not an easy task – we asked the people to raise their hands in the air and indicate with the number of fingers what is their level of confidence in the plan. One means no confidence at all, and five means excellent. As hands went up in the air we saw one One and a few Twos. Most were from one team. We asked the people what was the issue and the response we got was that everything got into the plan because this is what they were asked to do. Not good.

What the RTE did at this point was to allocate another 30 minutes for the teams to change their plans so they will believe in them. Stories were moved, features got a bit thinner and when we had the vote again, we had a few Threes and the rest were Fours and Fives. The number of Threes was small enough for us to decide to handle these issues during execution.

Retrospective

At the very end of the day, we asked the teams to present the main findings of their retrospective. The feedback was good, mainly that teams agreed on them when and who will do what is something that so far they couldn’t manage to do. This fast coordination loop is making things that would usually take weeks or months to happen in one day. And that’s magic!

Subscribe for Email Updates:

Categories:

Tags:

Kanban Kickstart Example
Pomodoro Technique
ATDD
Scrum and XP
Kanban Basics
Principles of Lean-Agile Leadership
Quality Assurance
Lean Budgeting
Agile Release Management
Keith Sawyer
Kaizen Workshop
Sprint Retrospectives
Frameworks
Implementation of Lean and Agile
Tools
ART Success
Kaizen
Agile Project
Lean and Agile Techniques
LeSS
Reading List
Perfection Game
Agile Israel Events
Self-organization
LPM
Agile Games
Operational Value Stream
Agile Games and Exercises
Team Flow
Amdocs
IT Operations
Agile for Embedded Systems
Webinar
Jira Cloud
Scrum.org
GanttBan
Spotify
Scrum Master
Nexus vs SAFe
Agile India
Scrum
Agile Testing Practices
Lean-Agile Software Development
Product Management
Kanban Game
Lean Startup
Risk Management on Agile Projects
Lean Agile Organization
Planning
SAFe DevOps
Limiting Work in Progress
Test Driven Development
DevOps
Entrepreneurial Operating System®
Agile Risk Management
SA
Scrum Primer
SAFe Release Planning
Scrum Guide
agileisrael
Process Improvement
Agile
predictability
Scrum With Kanban
Slides
Implementing SAFe
Hybrid Work
Rapid RTC
NIT
lean agile change management
ScrumMaster Tales
Agile Contracts Best Practices
Lean Agile Management
Scrum Master Role
chatgpt
Nexus Integration Team
Achieve Business Agility
WIP
Presentation
Enterprise DevOps
Sprint Iteration
Agile Techniques
ROI
User stories
A Kanban System for Software Engineering
The Agile Coach
Agile Program
Lean and Agile Principles and Practices
Engineering Practices
System Archetypes
Nexus
Sprint Planning
Covid19
Continuous Integration
AI
Continuous Deployment
TDD
Program Increment
Release Train Engineer
Large Scale Scrum
Continuous Improvement
Releases Using Lean
Applying Agile Methodology
Lean Agile
What Is Kanban
Agile and DevOps Journey
Video
Professional Scrum Product Owner
An Appreciative Retrospective
Lean-Agile Budgeting
Legacy Enterprise
Agile Exercises
Jira Plans
Elastic Leadership
Nexus and SAFe
Introduction to ATDD
Agile in the Enterprise
Agility
Daily Scrum
Agile Project Management
System Team
Lean Agile Basics
Agile Product Development
Jira
Value Streams
Agile Community
Artificial Intelligence
Agile Outsourcing
Lean Agile Leadership
Story Slicing
Code
Coaching Agile Teams
Continuous Planning
Atlaassian
Systems Thinking
Nexus and Kanban
Iterative Incremental Development
Managing Projects
ARTs
SPC
Agile Israel
Introduction to Test Driven Development
Agile Assembly Architecture
Agile Delivery
RSA
speed at scale
Games and Exercises
Certified SAFe
Kanban 101
Agile Release Planning
AgileSparks
System Integration Environments
AI Artificial Intelligence
Agile Basics
Built-In Quality
Continuous Delivery
The Kanban Method
Certification
Business Agility
Kanban
Development Value Streams
LAB
Lean Risk Management
Professional Scrum Master
Atlassian
Agile Product Ownership
RTE
Jira admin
EOS®
Professional Scrum with Kanban
Risk Management in Kanban
ALM Tools
Scrum Values
Manage Budget Creation
PI Objectives
Agile Development
Change Management
SAFe
QA
ATDD vs. BDD
POPM
Legacy Code
PI Planning
Accelerate Value Delivery At Scale
Risk-aware Product Development
Product Ownership
Advanced Roadmaps
Managing Risk on Agile Projects
Scaled Agile Framework
speed @ scale
Effective Agile Retrospectives
Tips
Software Development
Lean Software Development
BDD
Acceptance Test-Driven Development
Software Development Estimation
Agile Mindset
Agile Marketing
Portfolio for Jira
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart