I’d like to share with you some tips and tricks for setting up a scrum board I usually share with my clients. The bottom line is that too many tools have too many features that support old ways of thinking. Let’s look at the various items one by one.

Subtasks

Like the human tailbone, subtasks were once useful but are now mainly a source of pain. When we worked in Waterfall we measured progress with completed subtasks, but in agile when stories are short, subtasks are a burden.

A burden for developers who need to mess with subtasks using the ALM tool.

This a burden for managers who measure progress using a burndown chart that usually relies on subtasks estimation. That’s a burden because burndown charts may time tell an incorrect story (all work done but nothing is working) – progress should be measured by “done” stories, usually a burnup chart.

Using subtasks should be a choice given to developers. If you find it useful then use it. I prefer just discussing the work to be done with the other people working with me on a story. If needed we can write it down on a whiteboard, but usually, there is no need to write it down as the story is so short. We just do the job.

Showing subtasks on a scrum board takes the focus from stories getting done to subtasks. It makes the scrum board too clattered and worse of all it lets people focus on their specific job and not on the story getting done. Bad subtasks! Bad!

Swimlanes 

Another evil thing is swimlanes. Second only to subtasks.

People usually need swimlanes because there is too much information on the board. That’s indeed a problem. Many times it will be … subtasks! If it isn’t subtasks it may be either the stories are too small or the team is too big. Or maybe something else.

The idea is we need to see why are there too many items on the board and handle that problem.

The big problem with swimlanes is that it distracts you. When you have swimlanes it is difficult to see what is now in progress. This is because usually there will be items in the “to do” column which will make the swimlane too wide to see all the items in one column.

Your focus is on the things that are now in progress and that’s what you need to see.

Many times there is a swim lane per team member. This will hint that we are trying to make sure people are utilized. Like the manifesto would say, it is important to make sure people are utilized but it is more important to get stories done.

Sometimes team members ask for a swimlane per developer. This tells us that people really care only about what they need to do and not about the team. This brings us to the next item:

Story Assignee

Almost all tools allow one person to be assigned to a story. (Leankit allows many). If you want to assign more people you can use subtasks. However, we already discussed subtasks and the conclusion was quite clear.

We will usually need to assign more than one person. In many places, at least one developer and one QA will be assigned. More than that, we will be happy if people can swarm on stories – having several people working on one story is fun and contributes to teamwork and thus very effective.

So, what do we do?

Many tools allow the addition of custom fields. For instance, Jira. I usually recommend clients working with Jira add a custom field called “assigned team members”. The field type should be multi-select. You will need to manually add the list of all team members. Once you do that you ask the tool to present the information on the card on the board and suddenly – voila! You have a strong scrum board where you see the people involved in every story. That’s great.

Last but not least – Columns

Most tools start with the standard “To Do – Doing – Done” columns + a backlog. (read here about the critical difference between backlog and to-do). That’s great! Why touch it? Please don’t.

Many teams will add a “Test” column. And a “pull request” column. And there are more.

The problem with these additional columns is that they are good excuses for things getting stuck. If there is a “dev” column and a “Test” column it means it is really all right to finish dev (I’m done!) and QA can be done later. Reminds you of subtasks? correct, it is similar.

If the sprint is only two weeks long and stories are short, there should be no reason for these additional columns. Just get done with the story – and please no stories! Remember we already have the names of all involved people on the card – just get it done with.

Conclusion

A scrum board should be very simple. There is a list of stories to do. Some are in progress, some are already done. We know who is working on what. That’s it. Don’t let fancy features distract you.

You may be interested in one of our Agile Up! workshops where we help you use popular Agile ALM tools such as Jira and TFS more effectively.

Subscribe for Email Updates:

Categories:

Tags:

Tips
Agile
An Appreciative Retrospective
Planning
BDD
Change Management
ART Success
Accelerate Value Delivery At Scale
System Team
ALM Tools
AI Artificial Intelligence
NIT
Kanban Kickstart Example
Kaizen
RTE Role
Jira Plans
SA
Development Value Streams
Certified SAFe
Legacy Code
Spotify
Lean-Agile Budgeting
Agile Project Management
ROI
Kanban
Test Driven Development
Kanban 101
The Kanban Method
Introduction to ATDD
Lean Risk Management
Releases Using Lean
AgileSparks
Self-organization
The Agile Coach
Scrum Master
Agile Exercises
Enterprise DevOps
Lean Budgeting
Jira Cloud
Scrum Values
Agility
Agile Risk Management
Jira admin
Large Scale Scrum
Manage Budget Creation
predictability
Agile Product Development
Effective Agile Retrospectives
SAFe
chatgpt
Daily Scrum
Value Streams
QA
ARTs
LPM
Rapid RTC
SPC
Video
ATDD vs. BDD
Professional Scrum with Kanban
Entrepreneurial Operating System®
Scrum.org
Slides
Legacy Enterprise
POPM
Quality Assurance
speed @ scale
Agile Marketing
TDD
Lean-Agile Software Development
System Integration Environments
Kanban Basics
AI
Product Management
Agile Development
Pomodoro Technique
Nexus and SAFe
Kanban Game
Program Increment
Process Improvement
Professional Scrum Product Owner
Jira
Applying Agile Methodology
A Kanban System for Software Engineering
Iterative Incremental Development
Agile and DevOps Journey
WIP
Nexus Integration Team
Built-In Quality
Sprint Retrospectives
System Archetypes
Portfolio for Jira
Risk-aware Product Development
RSA
Product Ownership
Scrum Primer
Agile Product Ownership
DevOps
Agile Games and Exercises
Lean Agile Basics
SAFe Release Planning
LAB
Scrum
Agile Assembly Architecture
Principles of Lean-Agile Leadership
Operational Value Stream
LeSS
Lean Agile Organization
Agile Release Planning
Lean and Agile Techniques
ScrumMaster Tales
Continuous Improvement
Lean Software Development
Atlassian
Acceptance Test-Driven Development
Certification
Scaled Agile Framework
Agile Techniques
Risk Management in Kanban
Atlaassian
Frameworks
Continuous Delivery
speed at scale
Release Train Engineer
Lean and Agile Principles and Practices
Games and Exercises
Keith Sawyer
PI Objectives
Lean Agile Management
Sprint Planning
Coaching Agile Teams
IT Operations
Software Development Estimation
Managing Risk on Agile Projects
Sprint Iteration
ATDD
Code
Agile Release Management
Scrum Guide
Scrum With Kanban
Continuous Integration
Scrum Master Role
Agile Testing Practices
Story Slicing
Amdocs
Agile Mindset
Perfection Game
Risk Management on Agile Projects
Introduction to Test Driven Development
Hybrid Work
Artificial Intelligence
Covid19
Continuous Planning
Achieve Business Agility
Reading List
EOS®
Agile Outsourcing
Implementing SAFe
Agile Contracts Best Practices
lean agile change management
Agile Program
Webinar
GanttBan
What Is Kanban
Agile Community
Nexus and Kanban
Agile for Embedded Systems
Limiting Work in Progress
Scrum and XP
agileisrael
Nexus vs SAFe
Lean Agile Leadership
Advanced Roadmaps
Kaizen Workshop
Agile Israel Events
Professional Scrum Master
Tools
Elastic Leadership
Managing Projects
Agile Delivery
Agile in the Enterprise
Systems Thinking
User stories
Agile Basics
PI Planning
Agile India
Presentation
Nexus
Agile Israel
Software Development
Team Flow
Continuous Deployment
Lean Agile
RTE
Business Agility
Agile Project
Implementation of Lean and Agile
Agile Games
Engineering Practices
Lean Startup
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart