The horrible truth about software development estimation, and what to do about it

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

In recent years I’ve been working with many software development teams and almost all of them struggle with estimating the work. The energy spent on this and the frustration it causes should come to a halt. And so, in this short article, I combine knowledge gained by many people with my experience and explain how to address this.

A significant amount of time is spent on estimating the work required to build software. I’ve seen teams spending around two days every two weeks trying to understand how much the work will cost, with organizations spending valuable time of managers and experts haggling, pushing and fighting over estimations.

Does it work? Do they get the estimations right? No, they don’t. Why? Simply put, building software is complex. We think we know what’s ahead of us, but we just don’t. This is very difficult to grasp and accept. Requirements evolve. Design evolves. We gain understanding through the work. Things change all the time.

And so, as your expertise increases you come to the conclusion that, while it is usually possible to know the magnitude of order (hours/days/weeks), accurate estimation of the work in hours, days, weeks or months is almost impossible.

This is a great breakthrough, as once you understand this reality, that accurate estimation of software development is not possible, you can start moving forward.

What can be done? How can we have a prediction of when things will get done?

Reduce possibility of development going out of control

The key to the solution is to reduce the possibility of the development process getting out of control. Instead of trying to figure out how much effort it will take to develop features, we take two main measures to increase the predictability of our development process.

The first measure is keeping the batch size, the amount of requirements we develop, small enough. This is because the complexity of development increases at an exponential rate with the growth of the number of requirements.

The main question, therefore, when estimating work is not how much effort it is but rather is it in the right size. If it is too big we need to break it down to smaller pieces.

The right size may change from team to team according to several factors, but from my experience a software development team working with modern tools usually aims towards a few days per development item, something that can be demonstrated to a product manager.

Below see a cycle time control chart of a development team, produced from Jira Software. Each dot is one or more development items that ended on the time indicated by the X axis. The Y axis shows how long it took to develop that item. This team’s average cycle time is around 4 days, but from time to time There are items escaping that average – the team discusses these items in order to improve.

As written above, the first thing to do to handle the problem of estimating work items is to try and bring them down to a size the team is comfortable with. Whether it is 2, 3, or 4 days doesn’t matter – what matters is that it is more or less the team’s usual size, which gives plenty of space for changes during the actual development.

Increase development predictability

The second approach to adopt to increase development predictability is combining forces, working together as a team.

To handle the complexity of software development we use a whole team approach. The team plans its work and does it together. The approach of the team leader making the plan and then each team member getting an assignment that they work on alone doesn’t work.

Practically, what does “Teamwork” mean? It means planning together: the team looks at the scope of items, determines together whether they are small enough (see above), and decides on their forecast for the development period. The team then starts handling the various items. They take items according to priority and work on them together. Working on items together sometimes means working on two parallel streams of the same job, sometimes it means sitting together at one development machine (pairing). It means that according to need and priority people switch tasks to help their teammates, and in general, the team does whatever it takes to get the work done.

Here is an example of a team who moved from investing a lot of time (2 days per person per 2 weeks) on estimating to working together and avoiding exact estimation. The gray columns are how much was planned for a development period and the green columns are how much was actually done (the changes in throughput are due to personnel changes)

To summarize, instead of being heartbroken over spending endless time on estimation and not hitting the estimates, strive to break your work into smaller, lower complexity items and focus on teamwork. Software development work is thinking. And nothing beats thinking together.

(Photos by ThisisEngineering RAEng on Unsplash)

Subscribe for Email Updates:

Categories:

Tags:

Sprint Planning
Test Driven Development
Risk Management in Kanban
ARTs
GanttBan
LPM
Scrum
Scrum Guide
Sprint Retrospectives
Risk-aware Product Development
Lean Risk Management
Lean Agile Organization
NIT
SAFe Release Planning
Business Agility
User stories
Agility
Agile Contracts Best Practices
Agile Basics
Amdocs
Lean Agile
SA
Quality Assurance
Kanban Basics
Nexus Integration Team
Agile in the Enterprise
Agile Release Planning
ART Success
Process Improvement
Agile for Embedded Systems
PI Objectives
Agile Product Ownership
Agile Testing Practices
Nexus vs SAFe
speed @ scale
Agile Exercises
chatgpt
POPM
agileisrael
Managing Projects
Agile India
Enterprise DevOps
Applying Agile Methodology
Rapid RTC
Presentation
Lean Agile Management
Implementing SAFe
Story Slicing
Development Value Streams
System Integration Environments
Lean Startup
BDD
Daily Scrum
Nexus and Kanban
ALM Tools
Product Management
Team Flow
QA
Lean Software Development
Effective Agile Retrospectives
Portfolio for Jira
SAFe DevOps
Agile Israel
Scrum Values
Lean-Agile Software Development
Agile Risk Management
An Appreciative Retrospective
Introduction to Test Driven Development
Atlassian
Agile Delivery
Reading List
The Agile Coach
Hybrid Work
Jira Cloud
Jira Plans
Kaizen Workshop
Iterative Incremental Development
Agile
Agile Games and Exercises
AI
Agile Product Development
Scrum and XP
Artificial Intelligence
Code
Sprint Iteration
Jira
Spotify
Lean and Agile Principles and Practices
Legacy Code
Elastic Leadership
Webinar
SAFe
A Kanban System for Software Engineering
Scrum Master
Video
Frameworks
TDD
Entrepreneurial Operating System®
predictability
Manage Budget Creation
Agile Community
Value Streams
Planning
Lean-Agile Budgeting
Scrum Primer
Continuous Deployment
Scrum Master Role
Continuous Planning
Product Ownership
Systems Thinking
Scrum With Kanban
Agile Project
Lean Agile Leadership
Kanban 101
Certification
The Kanban Method
Legacy Enterprise
Kaizen
Agile Release Management
Coaching Agile Teams
Perfection Game
Software Development Estimation
Keith Sawyer
Agile Techniques
Kanban Kickstart Example
Tools
Certified SAFe
Games and Exercises
Kanban Game
RSA
Software Development
Professional Scrum Product Owner
Implementation of Lean and Agile
Operational Value Stream
Nexus
Tips
Releases Using Lean
WIP
Continuous Improvement
Agile Assembly Architecture
Agile Development
AI Artificial Intelligence
Covid19
Professional Scrum with Kanban
Continuous Integration
PI Planning
Achieve Business Agility
LAB
ATDD vs. BDD
Agile Project Management
Accelerate Value Delivery At Scale
Continuous Delivery
Agile Outsourcing
Slides
System Team
Principles of Lean-Agile Leadership
speed at scale
Lean Budgeting
ScrumMaster Tales
Lean Agile Basics
DevOps
Introduction to ATDD
Large Scale Scrum
Agile Marketing
ROI
RTE
EOS®
Change Management
Risk Management on Agile Projects
Self-organization
Managing Risk on Agile Projects
Scaled Agile Framework
Agile and DevOps Journey
Professional Scrum Master
Advanced Roadmaps
ATDD
Jira admin
Acceptance Test-Driven Development
Kanban
Agile Mindset
Atlaassian
Scrum.org
Nexus and SAFe
Limiting Work in Progress
System Archetypes
Program Increment
AgileSparks
Built-In Quality
Pomodoro Technique
Agile Games
RTE Role
lean agile change management
Lean and Agile Techniques
IT Operations
What Is Kanban
Agile Israel Events
SPC
Agile Program
Engineering Practices
LeSS
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart